5700 N RUDNICK AVE 91367
Certificate Information: 5700 N RUDNICK AVE 91367
- Application / Permit
- 22030-10000-06530
- Plan Check / Job No.
- B22LA19054
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (70) Grading - Hillside
- Work Description
- SITE GRADING FOR (N) BUILDING, PARKING LOT, AND RETAINING WALL
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/17/2025
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2022 | LAMAR DAVIS |
| Green Plans Picked Up | 9/26/2022 | APPLICANT |
| Corrections Issued | 9/27/2022 | LAMAR DAVIS |
| Quality Review Completed | 10/5/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 10/6/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 10/6/2022 | APPLICANT |
| Applicant returned to address corrections | 11/16/2022 | LAMAR DAVIS |
| Applicant returned to address corrections | 12/27/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/31/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/21/2023 | SINA KHOSRAVI |
| Applicant returned to address corrections | 6/27/2023 | SINA KHOSRAVI |
| Plan Check Approved | 7/6/2023 | SINA KHOSRAVI |
| Issued | 7/7/2023 | APPLICANT |
| Permit Finaled | 3/17/2025 | ROBERT PINA |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/16/2022 | LAMAR DAVIS |
| Grading in hillside | Cleared | 12/6/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 12/6/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 12/6/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 12/6/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 12/6/2022 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 5/14/2023 | ANDRES COVARRUBIAS |
| Grading Pre-Inspection | Cleared | 7/6/2023 | LAMAR DAVIS |
Contact Information
| Contractor | Parker Brown Inc; Lic. No.: 689613-B | 21116 VANOWEN STREET CANOGA PARK, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/12/2023 | Approved | ROBERT PINA |
| Bottom/Toe | 7/26/2023 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 7/26/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 7/27/2023 | Approved | BRIAN MILLER |
| Excavation | 7/27/2023 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 7/31/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 8/1/2023 | Approved | ROBERT PINA |
| Deputy Grading | 8/2/2023 | Approved | ROBERT PINA |
| Deputy Grading | 8/3/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 8/4/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 8/9/2023 | Approved | ROBERT PINA |
| Bottom/Toe | 8/10/2023 | Partial Approval | ROBERT PINA |
| Deputy Grading | 8/10/2023 | Approved | ROBERT PINA |
| Deputy Grading | 8/11/2023 | Approved | ROBERT PINA |
| Initial Grading | 8/14/2023 | No Access for Inspection | BRIAN MILLER |
| Deputy Grading | 8/18/2023 | Approved | ROBERT PINA |
| Deputy Grading | 8/24/2023 | Approved | BRIAN MILLER |
| Initial Grading | 8/31/2023 | Partial Approval | BRIAN MILLER |
| Rough | 8/31/2023 | Partial Inspection | BRIAN MILLER |
| Deputy Grading | 9/5/2023 | Approved | BRIAN MILLER |
| Excavation | 9/6/2023 | Approved | ROBERT PINA |
| Deputy Grading | 9/20/2023 | Approved | ROBERT PINA |
| Deputy Grading | 9/25/2023 | Approved | ROBERT PINA |
| Deputy Grading | 11/9/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 11/13/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 11/27/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 11/28/2023 | Approved | ROBERT PINA |
| Deputy Grading | 11/29/2023 | Approved | BRIAN MILLER |
| Bottom/Toe | 11/30/2023 | Corrections Issued | BRIAN MILLER |
| Deputy Grading | 11/30/2023 | Approved | BRIAN MILLER |
| Excavation | 11/30/2023 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 12/1/2023 | Approved | BRIAN MILLER |
| Deputy Grading | 12/4/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 12/5/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/8/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/11/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/12/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 12/13/2023 | Partial Approval | BRIAN MILLER |
| Deputy Grading | 12/13/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/14/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/15/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/18/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/19/2023 | No Access for Inspection | ROBERT PINA |
| Deputy Grading | 12/20/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 12/22/2023 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 1/11/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 3/20/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/14/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/15/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/16/2024 | Approved | ALEXANDER HELFER |
| Deputy Grading | 5/17/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/20/2024 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/21/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 5/21/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/22/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/23/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/24/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/28/2024 | Approved | ALEXANDER HELFER |
| Bottom/Toe | 5/29/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/29/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 5/29/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/30/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/31/2024 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Grading | 6/4/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/5/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/6/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/7/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/12/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 6/13/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/13/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 6/14/2024 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 7/16/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 12/11/2024 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 1/22/2025 | Approved | ROBERT PINA |
| Bottom/Toe | 3/17/2025 | Approved | ROBERT PINA |
| Final | 3/17/2025 | Permit Finaled | ROBERT PINA |
| Rough | 3/17/2025 | Approved | ROBERT PINA |