5700 N RUDNICK AVE 91367

Certificate Information: 5700 N RUDNICK AVE 91367

Application / Permit
22030-10000-06530
Plan Check / Job No.
B22LA19054
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING FOR (N) BUILDING, PARKING LOT, AND RETAINING WALL
Permit Issued
Issued on 7/7/2023
Issuing Office
Current Status
Permit Finaled on 3/17/2025

Permit Application Status History

Submitted 9/21/2022 APPLICANT
Assigned to Plan Check Engineer 9/22/2022 LAMAR DAVIS
Green Plans Picked Up 9/26/2022 APPLICANT
Corrections Issued 9/27/2022 LAMAR DAVIS
Quality Review Completed 10/5/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 10/6/2022 APPLICANT
Disabled Access Plans Picked Up 10/6/2022 APPLICANT
Applicant returned to address corrections 11/16/2022 LAMAR DAVIS
Applicant returned to address corrections 12/27/2022 SINA KHOSRAVI
Applicant returned to address corrections 5/31/2023 SINA KHOSRAVI
Applicant returned to address corrections 6/21/2023 SINA KHOSRAVI
Applicant returned to address corrections 6/27/2023 SINA KHOSRAVI
Plan Check Approved 7/6/2023 SINA KHOSRAVI
Issued 7/7/2023 APPLICANT
Permit Finaled 3/17/2025 ROBERT PINA

Permit Application Clearance Information

Miscellaneous Cleared 11/16/2022 LAMAR DAVIS
Grading in hillside Cleared 12/6/2022 SPENCER WEJROWSKI
ZA Case Cleared 12/6/2022 SPENCER WEJROWSKI
ZA Case Cleared 12/6/2022 SPENCER WEJROWSKI
ZA Case Cleared 12/6/2022 SPENCER WEJROWSKI
ZA Case Cleared 12/6/2022 SPENCER WEJROWSKI
Low Impact Development Cleared 5/14/2023 ANDRES COVARRUBIAS
Grading Pre-Inspection Cleared 7/6/2023 LAMAR DAVIS

Contact Information

Contractor Parker Brown Inc; Lic. No.: 689613-B 21116 VANOWEN STREET      CANOGA PARK, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/12/2023 Approved ROBERT PINA
Bottom/Toe 7/26/2023 Partial Approval BRIAN MILLER
Deputy Grading 7/26/2023 Approved BRIAN MILLER
Deputy Grading 7/27/2023 Approved BRIAN MILLER
Excavation 7/27/2023 Partial Approval BRIAN MILLER
Deputy Grading 7/31/2023 Approved BRIAN MILLER
Deputy Grading 8/1/2023 Approved ROBERT PINA
Deputy Grading 8/2/2023 Approved ROBERT PINA
Deputy Grading 8/3/2023 Approved BRIAN MILLER
Deputy Grading 8/4/2023 Approved BRIAN MILLER
Deputy Grading 8/9/2023 Approved ROBERT PINA
Bottom/Toe 8/10/2023 Partial Approval ROBERT PINA
Deputy Grading 8/10/2023 Approved ROBERT PINA
Deputy Grading 8/11/2023 Approved ROBERT PINA
Initial Grading 8/14/2023 No Access for Inspection BRIAN MILLER
Deputy Grading 8/18/2023 Approved ROBERT PINA
Deputy Grading 8/24/2023 Approved BRIAN MILLER
Initial Grading 8/31/2023 Partial Approval BRIAN MILLER
Rough 8/31/2023 Partial Inspection BRIAN MILLER
Deputy Grading 9/5/2023 Approved BRIAN MILLER
Excavation 9/6/2023 Approved ROBERT PINA
Deputy Grading 9/20/2023 Approved ROBERT PINA
Deputy Grading 9/25/2023 Approved ROBERT PINA
Deputy Grading 11/9/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 11/13/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 11/27/2023 Approved BRIAN MILLER
Deputy Grading 11/28/2023 Approved ROBERT PINA
Deputy Grading 11/29/2023 Approved BRIAN MILLER
Bottom/Toe 11/30/2023 Corrections Issued BRIAN MILLER
Deputy Grading 11/30/2023 Approved BRIAN MILLER
Excavation 11/30/2023 Partial Approval BRIAN MILLER
Deputy Grading 12/1/2023 Approved BRIAN MILLER
Deputy Grading 12/4/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Drainage Devices/Catch Basin 12/5/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/8/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/11/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/12/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 12/13/2023 Partial Approval BRIAN MILLER
Deputy Grading 12/13/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/14/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/15/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/18/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/19/2023 No Access for Inspection ROBERT PINA
Deputy Grading 12/20/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 12/22/2023 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Grading 1/11/2024 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 3/20/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/14/2024 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/15/2024 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/16/2024 Approved ALEXANDER HELFER
Deputy Grading 5/17/2024 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/20/2024 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/21/2024 Approved GERMAN RODRIGUEZ MENDOZA
Drainage Devices/Catch Basin 5/21/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/22/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/23/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/24/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/28/2024 Approved ALEXANDER HELFER
Bottom/Toe 5/29/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/29/2024 Approved GERMAN RODRIGUEZ MENDOZA
Sub-Drain 5/29/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/30/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 5/31/2024 Conditional Approval RUSSELL BONVOULOIR
Deputy Grading 6/4/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/5/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/6/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/7/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/12/2024 Approved GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 6/13/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/13/2024 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Grading 6/14/2024 Approved GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 7/16/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drainage Devices/Catch Basin 12/11/2024 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 1/22/2025 Approved ROBERT PINA
Bottom/Toe 3/17/2025 Approved ROBERT PINA
Final 3/17/2025 Permit Finaled ROBERT PINA
Rough 3/17/2025 Approved ROBERT PINA