5345 W 99TH ST 90045
Certificate Information: 5345 W 99TH ST 90045
- Application / Permit
- 22030-10000-05425
- Plan Check / Job No.
- B22LA15376
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- **ePlan**LAX-LAMP Project** Excavation to install detention basin for LAX Rental Car Facility (ConRAC).
- Permit Issued
- Issued on 7/13/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/25/2025
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/11/2022 | GARO TELMI |
| Corrections Issued | 8/18/2022 | DEAN RYAN REYES |
| Applicant returned to address corrections | 10/11/2022 | DEAN RYAN REYES |
| Applicant returned to address corrections | 10/14/2022 | DEAN RYAN REYES |
| Applicant returned to address corrections | 6/24/2023 | GARO TELMI |
| Plan Check Approved | 7/11/2023 | GARO TELMI |
| Issued | 7/13/2023 | APPLICANT |
| Permit Finaled | 11/24/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| Project Permit | Cleared | 9/19/2022 | DEAN RYAN REYES |
| City owned building/parcel | Cleared | 9/22/2022 | DEAN RYAN REYES |
| Excavation more than 5-ft deep | Cleared | 10/12/2022 | CALOSHA APPROVED |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | MARYAM AZARBAYJANI |
| Low Impact Development | Cleared | 11/29/2022 | AMMAR ELTAWIL |
| Work Adjacent to Public Way | Cleared | 6/7/2023 | MARYAM AZARBAYJANI |
| Roof/Waste drainage to street | Cleared | 6/14/2023 | MAHELET GEBEYHU |
Contact Information
| Contractor | Skanska Usa Civil West California District Inc; Lic. No.: 140069-A | 1995 AGUA MANSA RD RIVERSIDE, CA 92509 |
| Engineer | Mones,, Ronald N; Lic. No.: C75506 | 311 E GLENARM STREET APT6 PASADENA, CA 91106 |
Inspector Information
| JESUS RODRIGUEZ, (213) 216-1187 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 11/3/2023 | Approved | AL GAMBLE |
| Initial Grading | 11/3/2023 | Approved | AL GAMBLE |
| Initial Grading | 11/16/2023 | Approved | AL GAMBLE |
| Deputy Grading | 11/17/2023 | Approved | AL GAMBLE |
| Deputy Grading | 11/20/2023 | Partial Approval | AL GAMBLE |
| Deputy Grading | 11/21/2023 | Approved | AL GAMBLE |
| Deputy Grading | 11/22/2023 | No Access for Inspection | MATTHEW JENKINS |
| Deputy Grading | 11/27/2023 | No Access for Inspection | MATTHEW JENKINS |
| Deputy Grading | 12/5/2023 | Approved | AL GAMBLE |
| Deputy Grading | 12/6/2023 | Conditional Approval | AL GAMBLE |
| Deputy Grading | 12/7/2023 | Conditional Approval | AL GAMBLE |
| Deputy Grading | 12/8/2023 | Approved | AL GAMBLE |
| Excavation | 12/8/2023 | Not Ready for Inspection | AL GAMBLE |
| Deputy Grading | 12/11/2023 | No Access for Inspection | VASIL MIHALEV |
| Fill/Backfill | 1/2/2024 | Partial Inspection | AL GAMBLE |
| Approved Compaction Report | 3/5/2024 | Not Ready for Inspection | AL GAMBLE |
| Bottom/Toe | 3/5/2024 | Not Ready for Inspection | AL GAMBLE |
| Final | 3/5/2024 | Not Ready for Inspection | AL GAMBLE |
| Rough | 3/5/2024 | Not Ready for Inspection | AL GAMBLE |
| Approved Compaction Report | 2/5/2025 | Corrections Issued | VASIL MIHALEV |
| Approved Compaction Report | 8/4/2025 | Not Ready for Inspection | LANNY MERRICK |
| Bottom/Toe | 10/17/2025 | Approved | MATTHEW JENKINS |
| Final | 10/17/2025 | Corrections Issued | MATTHEW JENKINS |
| Rough | 10/17/2025 | Approved | MATTHEW JENKINS |
| Final | 11/24/2025 | Permit Finaled | RUSSELL BONVOULOIR |