2565 S PATRICIA AVE 90064

Certificate Information: 2565 S PATRICIA AVE 90064

Application / Permit
22030-10000-05401
Plan Check / Job No.
B22LA15312
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(60) Grading - Non-Hillside
Work Description
SITE GRADING FOR (N) SFD WITH BASEMENT, (N) RETAINING WALLS AND (N) POOL. 2 of 4
Permit Issued
Issued on 4/13/2023
Issuing Office
Valley
Current Status
Permit Finaled on 2/28/2025

Permit Application Status History

Submitted 8/3/2022 APPLICANT
Assigned to Plan Check Engineer 8/11/2022 ADRIANA LOPEZ
Corrections Issued 9/6/2022 ADRIANA LOPEZ
Quality Review Completed 9/16/2022 FARUK SEZER
Building Plans Picked Up 9/22/2022 APPLICANT
Applicant returned to address corrections 1/26/2023 ADRIANA LOPEZ
Applicant returned to address corrections 2/24/2023 ADRIANA LOPEZ
Plan Check Approved 3/17/2023 ADRIANA LOPEZ
Issued 4/13/2023 APPLICANT
Permit Finaled 2/27/2025 JOHNNY MIRANDA

Permit Application Clearance Information

ZI Cleared 2/13/2023 JASON CHAN
Hold Cleared 4/19/2023 MARIA VENDIVIL

Contact Information

Contractor Zeidan Nabil R; Lic. No.: 1078391-B 8886 DEERWEED CIR      CORONA, CA 92883
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 7/26/2023 Approved MATTHEW JENKINS
Deputy Grading 7/31/2023 No Access for Inspection VASIL MIHALEV
Deputy Grading 8/1/2023 Conditional Approval MATTHEW JENKINS
Excavation 8/2/2023 Partial Inspection MATTHEW JENKINS
Deputy Grading 8/3/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 8/4/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 8/7/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/2/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/11/2023 Conditional Approval MATTHEW JENKINS
Deputy Grading 10/12/2023 Conditional Approval MATTHEW JENKINS
Sub-Drain 11/1/2023 Conditional Approval MATTHEW JENKINS
Rough 12/5/2023 Not Ready for Inspection AL GAMBLE
Drainage Devices/Catch Basin 12/28/2023 Partial Approval JOHNNY MIRANDA
Sub-Drain 2/27/2024 Approved ROBERT PINA
Bottom/Toe 9/20/2024 Partial Inspection MATTHEW JENKINS
Bottom/Toe 9/24/2024 Partial Approval MATTHEW JENKINS
Bottom/Toe 11/27/2024 Partial Inspection MATTHEW JENKINS
Sub-Drain 11/27/2024 Partial Inspection MATTHEW JENKINS
Drainage Devices/Catch Basin 1/10/2025 Partial Approval AL GAMBLE
Approved Compaction Report 2/25/2025 Approved JOHNNY MIRANDA
Bottom/Toe 2/27/2025 Approved JOHNNY MIRANDA
Final 2/27/2025 Permit Finaled JOHNNY MIRANDA
Rough 2/27/2025 Approved JOHNNY MIRANDA