9200 N WINNETKA AVE 91311
Certificate Information: 9200 N WINNETKA AVE 91311
- Application / Permit
- 22030-10000-05151
- Plan Check / Job No.
- B21LA01742
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING FOR NEW MIXED USE BUILDING
- Permit Issued
- Issued on 8/2/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/19/2024
Permit Application Status History
| Submitted | 3/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/11/2021 | KEVIN MORALES |
| Corrections Issued | 3/30/2021 | KEVIN MORALES |
| Quality Review Completed | 4/1/2021 | EUGENE BARBEAU |
| Building Plans Picked Up | 4/8/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 7/21/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 9/1/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 5/18/2022 | KEVIN MORALES |
| Plan Check Approved | 7/22/2022 | KEVIN MORALES |
| Issued | 8/2/2022 | APPLICANT |
| Permit Finaled | 9/18/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Uncommon Builders Llc; Lic. No.: 1046026-B | 9220 WINNETKA AVE CHATSWORTH, CA 91311 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Bottom/Toe | 9/26/2022 | Partial Approval | BRIAN MILLER |
| Rough | 9/26/2022 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 12/16/2022 | Partial Approval | MANUEL TEJADA |
| Excavation | 12/16/2022 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 12/28/2022 | Approved | ALEXANDER HELFER |
| Excavation | 12/28/2022 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 12/30/2022 | Approved | ALEXANDER HELFER |
| Excavation | 2/6/2023 | Approved | ROBERT PINA |
| Fill/Backfill | 2/6/2023 | Partial Approval | ROBERT PINA |
| Rough | 2/6/2023 | Approved | ROBERT PINA |
| Final | 2/9/2023 | Partial Approval | ROBERT PINA |
| Final | 2/13/2023 | Partial Approval | ROBERT PINA |
| Sub-Drain | 3/22/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 4/23/2024 | Partial Approval | ROBERT PINA |
| Drainage Devices/Catch Basin | 5/10/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 6/12/2024 | No Access for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 6/12/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Fill/Backfill | 6/27/2024 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Approved Compaction Report | 8/15/2024 | Approved | MANUEL TEJADA |
| Final | 9/10/2024 | Not Ready for Inspection | CHARLES POWELL |
| Final | 9/18/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |