3748 N BERRY DR 91604
Certificate Information: 3748 N BERRY DR 91604
- Application / Permit
- 22030-10000-05031
- Plan Check / Job No.
- B22LA12367
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- ePLan Grading for new SFD over basement with attached garage and ADU
- Permit Issued
- Issued on 3/6/2023
- Issuing Office
- Current Status
- Permit Finaled on 3/7/2025
Permit Application Status History
| Submitted | 6/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | JAD BASMA |
| Corrections Issued | 7/16/2022 | JAD BASMA |
| Quality Review Completed | 7/28/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 8/23/2022 | JAD BASMA |
| Applicant returned to address corrections | 9/9/2022 | JAD BASMA |
| Applicant returned to address corrections | 10/12/2022 | JAD BASMA |
| Plan Check Approved | 2/14/2023 | JAD BASMA |
| Issued | 3/6/2023 | APPLICANT |
| Permit Finaled | 3/7/2025 | MANUEL TEJADA |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 2/8/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 2/8/2023 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 3/13/2023 | Not Ready for Inspection | ROBERT PINA |
| Drainage Devices/Catch Basin | 9/28/2023 | Corrections Issued | MANUEL TEJADA |
| SWPPP-Const. Storm Water | 9/28/2023 | Violation Observed | MANUEL TEJADA |
| Bottom/Toe | 10/29/2024 | Corrections Issued | RUSSELL BONVOULOIR |
| Final | 10/29/2024 | Not Ready for Inspection | RUSSELL BONVOULOIR |
| Rough | 10/29/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Approved Compaction Report | 12/11/2024 | Approved | MANUEL TEJADA |
| Bottom/Toe | 1/14/2025 | Partial Inspection | ALEXANDER HELFER |
| Final | 1/14/2025 | Partial Inspection | ALEXANDER HELFER |
| Rough | 1/14/2025 | Partial Inspection | ALEXANDER HELFER |
| Bottom/Toe | 1/27/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 1/27/2025 | Corrections Issued | MANUEL TEJADA |
| Rough | 1/27/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 2/7/2025 | Corrections Issued | MANUEL TEJADA |
| Bottom/Toe | 2/28/2025 | Partial Approval | MANUEL TEJADA |
| Final | 2/28/2025 | Corrections Issued | MANUEL TEJADA |
| Rough | 2/28/2025 | Partial Approval | MANUEL TEJADA |
| Bottom/Toe | 3/7/2025 | Approved | MANUEL TEJADA |
| Final | 3/7/2025 | Permit Finaled | MANUEL TEJADA |
| Rough | 3/7/2025 | Approved | MANUEL TEJADA |