7736 N HASKELL AVE 91406
Certificate Information: 7736 N HASKELL AVE 91406
- Application / Permit
- 22030-10000-04830
- Plan Check / Job No.
- B19LA18622
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- Grading Removal and Recompaction for (N) 3-STORY FULLY SPRINKLERED SELF STORAGE FACILITY PER ZA-2018-6899-CU-SPR-CLQ
- Permit Issued
- Issued on 7/11/2022
- Issuing Office
- Current Status
- Permit Finaled on 10/17/2023
Permit Application Status History
| Submitted | 9/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2019 | HERNAN ARREOLA |
| Corrections Issued | 10/3/2019 | HERNAN ARREOLA |
| Quality Review Completed | 10/4/2019 | BILL STUTSMAN |
| Applicant returned to address corrections | 9/15/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 10/14/2020 | APPLICANT |
| Applicant returned to address corrections | 11/12/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/19/2021 | HERNAN ARREOLA |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Issued | 7/11/2022 | APPLICANT |
| Permit Finaled | 10/16/2023 | BRIAN MILLER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Viole' T Construction Co Inc; Lic. No.: 283354-B | 18716 OXNARD ST TARZANA, CA 91356 |
| Engineer | Baroonian,, Armen; Lic. No.: S4227 | 867 N FAIR OAKS AVE 100 PASADENA, CA 91103 |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 7/12/2022 | Approved | LANNY MERRICK |
| Bottom/Toe | 7/18/2022 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 7/22/2022 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 7/26/2022 | Partial Approval | BRIAN MILLER |
| Excavation | 7/27/2022 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 7/28/2022 | Partial Approval | LANNY MERRICK |
| Excavation | 7/29/2022 | Partial Approval | BRIAN MILLER |
| Excavation | 8/1/2022 | Partial Approval | BRIAN MILLER |
| Fill/Backfill | 8/2/2022 | Partial Approval | LANNY MERRICK |
| Rough | 8/3/2022 | Partial Approval | BRIAN MILLER |
| Excavation | 8/4/2022 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 8/5/2022 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 8/9/2022 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 8/10/2022 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 8/11/2022 | Partial Approval | LANNY MERRICK |
| Approved Compaction Report | 8/17/2022 | Partial Approval | BRIAN MILLER |
| Approved Compaction Report | 8/18/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 9/1/2022 | Corrections Issued | BRIAN MILLER |
| Drainage Devices/Catch Basin | 10/3/2022 | No Access for Inspection | MANUEL TEJADA |
| Sub-Drain | 10/4/2022 | Partial Approval | LANNY MERRICK |
| Drainage Devices/Catch Basin | 10/5/2022 | Corrections Issued | MANUEL TEJADA |
| Sub-Drain | 10/7/2022 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 4/7/2023 | Partial Approval | ROBERT PINA |
| Drainage Devices/Catch Basin | 4/11/2023 | Partial Approval | BRIAN MILLER |
| Bottom/Toe | 9/8/2023 | Approved | ROBERT PINA |
| Final | 9/8/2023 | Not Ready for Inspection | ROBERT PINA |
| Rough | 9/8/2023 | Approved | ROBERT PINA |
| Approved Compaction Report | 9/29/2023 | Approved | BRIAN MILLER |
| Final | 10/16/2023 | Permit Finaled | BRIAN MILLER |