1661 N SAN ONOFRE DR 90272

Certificate Information: 1661 N SAN ONOFRE DR 90272

Application / Permit
22030-10000-04709
Plan Check / Job No.
B22LA09754
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR RETAINING WALL
Permit Issued
Issued on 10/14/2022
Issuing Office
Current Status
Permit Finaled on 11/20/2023

Permit Application Status History

Submitted 5/23/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 CRYSTEL MAALOUF
Corrections Issued 7/5/2022 CRYSTEL MAALOUF
Quality Review Completed 7/18/2022 FARUK SEZER
Applicant returned to address corrections 9/12/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 9/21/2022 CRYSTEL MAALOUF
Plan Check Approved 9/30/2022 CRYSTEL MAALOUF
Issued 10/14/2022 APPLICANT
Permit Finaled 11/20/2023 JOHNNY MIRANDA

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 9/30/2022 CALOSHA APPROVED
GPI Written Notices Cleared 9/30/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 9/30/2022 CRYSTEL MAALOUF

Contact Information

Contractor Marmol Radziner An Architectural Corporation; Lic. No.: 734381-B 12210 NEBRASKA AVENUE      LOS ANGELES, CA 90025
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

RAMAZANALI ALMASI, (310) 914-3899 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 10/18/2022 Approved TIMOTHY POWELL
Special/Order Compliance 10/27/2022 Partial Approval TIMOTHY POWELL
Deputy Grading 11/14/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/15/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/16/2022 Approved JONATHAN HOM
Deputy Grading 11/17/2022 Conditional Approval TIMOTHY POWELL
Deputy Grading 11/18/2022 Approved CHARLES POWELL
Deputy Grading 11/23/2022 Approved JONATHAN HOM
Deputy Grading 12/1/2022 Partial Approval MICHAEL TEMPLE
Drainage Devices/Catch Basin 3/17/2023 Partial Approval RUSSELL BONVOULOIR
Bottom/Toe 11/1/2023 Corrections Issued JOHNNY MIRANDA
Final 11/1/2023 Corrections Issued JOHNNY MIRANDA
Rough 11/1/2023 Partial Inspection JOHNNY MIRANDA
Approved Compaction Report 11/16/2023 Approved JOHNNY MIRANDA
Bottom/Toe 11/20/2023 Approved JOHNNY MIRANDA
Final 11/20/2023 Permit Finaled JOHNNY MIRANDA
Rough 11/20/2023 Approved JOHNNY MIRANDA