1655 N ALLESANDRO ST 90026

Certificate Information: 1655 N ALLESANDRO ST 90026

Application / Permit
22030-10000-03904
Plan Check / Job No.
B21LA15683
Group
Building
Type
Grading
Sub-Type
Apartment
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW APARTMENT. Board File 220056 APPROVED FOR AN EXPORT OF 1,800 CUBIC YARDS
Permit Issued
Issued on 2/28/2024
Issuing Office
Valley
Current Status
Permit Finaled on 5/1/2026

Permit Application Status History

Plan Check Approved 5/23/2023 KEVIN MORALES
Issued 2/28/2024 APPLICANT
Permit Finaled 5/1/2026 RAMAZANALI ALMASI

Permit Application Clearance Information

GPI Written Notices Cleared 1/5/2023 KEVIN MORALES
Grading Pre-Inspection Cleared 1/5/2023 KEVIN MORALES
"Q" conditions Cleared 4/20/2023 JAZMIN ROQUE
Miscellaneous Cleared 4/20/2023 JAZMIN ROQUE
Haul Route Cleared 5/22/2023 KARL MUHS

Contact Information

Contractor Aster Construction Services; Lic. No.: 976915-B 1666 1/2 MCCADDEN PLACE      LOS ANGELES, CA 90028

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 3/4/2024 Corrections Issued RUSSELL BONVOULOIR
Special/Order Compliance 3/5/2024 Corrections Issued RUSSELL BONVOULOIR
Initial Grading 3/8/2024 Approved RUSSELL BONVOULOIR
Excavation 3/18/2024 Not Ready for Inspection LANNY MERRICK
Bottom/Toe 3/20/2024 Partial Approval ALEXANDER HELFER
Excavation 3/20/2024 Approved ALEXANDER HELFER
Bottom/Toe 3/28/2024 Partial Approval ALEXANDER HELFER
Bottom/Toe 4/5/2024 Corrections Issued RUSSELL BONVOULOIR
Bottom/Toe 4/9/2024 Partial Inspection RUSSELL BONVOULOIR
Bottom/Toe 5/3/2024 Approved RUSSELL BONVOULOIR
Excavation 5/3/2024 Partial Approval RUSSELL BONVOULOIR
Approved Compaction Report 6/6/2024 Approved LANNY MERRICK
Rough 6/6/2024 Partial Inspection RUSSELL BONVOULOIR
Drainage Devices/Catch Basin 9/23/2024 Corrections Issued RUSSELL BONVOULOIR
Irrigation/Landscape 9/23/2024 Partial Inspection RUSSELL BONVOULOIR
Special/Order Compliance 9/26/2025 Corrections Issued RUSSELL BONVOULOIR
Fill/Backfill 11/6/2025 Not Ready for Inspection RUSSELL BONVOULOIR
Sub-Drain 11/7/2025 Partial Approval RAMAZANALI ALMASI
Final 4/24/2026 Corrections Issued RAMAZANALI ALMASI
Rough 4/24/2026 Not Ready for Inspection RAMAZANALI ALMASI
Approved Compaction Report 4/28/2026 Not Ready for Inspection RAMAZANALI ALMASI
Approved Compaction Report 4/30/2026 Approved RAMAZANALI ALMASI
Final 5/1/2026 Permit Finaled RAMAZANALI ALMASI
Rough 5/1/2026 Approved RAMAZANALI ALMASI