1353 N WESTERN AVE 90027
Certificate Information: 1353 N WESTERN AVE 90027
- Application / Permit
- 22030-10000-02739
- Plan Check / Job No.
- B22LA06819
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- SITE GRADING FOR (N) MIXED-USE APARTMENT COMPLEX. 6,610 CY CUT, 0 CY FILL , R&R 2,700 C.Y., AND 6,340 CY NET EXPORT UNDER 21010-10000-00711.
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/10/2023
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2022 | ARMEN JIVALAGIAN |
| Corrections Issued | 5/17/2022 | ARMEN JIVALAGIAN |
| Quality Review Completed | 5/18/2022 | KEN GILL |
| Building Plans Picked Up | 5/20/2022 | APPLICANT |
| Plan Check Approved | 12/21/2022 | ARMEN JIVALAGIAN |
| Issued | 1/10/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Vcc Construction Corp; Lic. No.: 961705-B | P O BOX 2558 LITTLE ROCK, AR 72203 |
| Engineer | Benichou,, Ety; Lic. No.: S5263 | 888 S FIGUEROA ST 18TH FLOOR LOS ANGELES, CA 90017 |
| Engineer | Knur,, Reinard Thomas; Lic. No.: GE2755 | 1435 MONCADO DR GLENDALE, CA 91207 |
| Engineer | Krief,, Dan D; Lic. No.: C76041 | 6420 WILSHIRE BLVD STE 1000 LOS ANGELES, CA 90048 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 1/20/2023 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 1/20/2023 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 2/14/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 2/15/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 2/16/2023 | Approved | JONATHAN HOM |
| Excavation | 2/16/2023 | Not Ready for Inspection | JONATHAN HOM |
| Deputy Grading | 2/17/2023 | Approved | KIRK LINKLATER |
| Deputy Grading | 2/21/2023 | Conditional Approval | JONATHAN HOM |
| Excavation | 4/4/2023 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 4/13/2023 | Not Ready for Inspection | JONATHAN HOM |
| Excavation | 4/13/2023 | Not Ready for Inspection | JONATHAN HOM |
| Sub-Drain | 4/13/2023 | Not Ready for Inspection | JONATHAN HOM |
| Excavation | 4/18/2023 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 4/20/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 4/21/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 4/24/2023 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 4/25/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 4/26/2023 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 4/26/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 4/27/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 4/28/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 5/1/2023 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 5/1/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/2/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/3/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/4/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/5/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/8/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 5/9/2023 | Approved | JONATHAN HOM |
| Fill/Backfill | 5/9/2023 | Partial Inspection | JONATHAN HOM |
| Deputy Grading | 5/12/2023 | Approved | JONATHAN HOM |
| Excavation | 7/12/2023 | Partial Inspection | JONATHAN HOM |
| Bottom/Toe | 7/20/2023 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 7/20/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 7/24/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 7/25/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 7/26/2023 | Approved | JONATHAN HOM |
| Bottom/Toe | 7/31/2023 | Partial Approval | JONATHAN HOM |
| Deputy Grading | 7/31/2023 | Approved | JONATHAN HOM |
| Deputy Grading | 8/3/2023 | Approved | JONATHAN HOM |
| Excavation | 8/3/2023 | Partial Approval | JONATHAN HOM |
| Bottom/Toe | 8/4/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 8/4/2023 | Approved | JONATHAN HOM |
| Excavation | 8/4/2023 | Approved | ALEXANDER HELFER |
| Drainage Devices/Catch Basin | 8/14/2023 | Partial Inspection | JONATHAN HOM |
| Special/Order Compliance | 8/14/2023 | Partial Inspection | JONATHAN HOM |
| Special/Order Compliance | 10/18/2023 | Partial Inspection | JONATHAN HOM |
| Excavation | 3/12/2024 | Partial Inspection | JONATHAN HOM |
| Excavation | 2/13/2025 | No Access for Inspection | JONATHAN HOM |