9433 N SEPULVEDA BLVD 91343
Certificate Information: 9433 N SEPULVEDA BLVD 91343
- Application / Permit
- 22030-10000-02304
- Plan Check / Job No.
- G22LA00031
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING PERMIT FOR PROPOSED 75-UNIT CONDOMINIUM PER VTT-73939. CUT = 18, 136 CY., FILL = 20,654 CY., IMPORT = 2,518 CY.
- Permit Issued
- Issued on 9/14/2022
- Issuing Office
- Current Status
- Issued on 9/14/2022
Permit Application Status History
| Submitted | 3/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2022 | DAN RYAN EVANGELISTA |
| Corrections Issued | 4/4/2022 | DAN RYAN EVANGELISTA |
| Applicant returned to address corrections | 9/2/2022 | DAN RYAN EVANGELISTA |
| Plan Check Approved | 9/12/2022 | DAN RYAN EVANGELISTA |
| Issued | 9/14/2022 | APPLICANT |
| Permit Expired-Status Void | 10/6/2022 | BRIAN MILLER |
| Re-Activate Permit | 10/11/2022 | BRIAN MILLER |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2022 | CARLOS AGUILERA |
| Excavation more than 5-ft deep | Cleared | 7/21/2022 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 7/21/2022 | CARLOS AGUILERA |
| Stormwater Pollution Mitigatn | Cleared | 7/28/2022 | ORVAL HERNANDEZ-MARCI |
| "Q" conditions | Cleared | 8/1/2022 | RUBEN VASQUEZ |
| "T" removal | Cleared | 8/1/2022 | RUBEN VASQUEZ |
| Private street | Cleared | 8/1/2022 | RUBEN VASQUEZ |
| Tract Map conditions | Cleared | 8/1/2022 | RUBEN VASQUEZ |
| Low Impact Development | Cleared | 8/23/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 8/24/2022 | CARLOS AGUILERA |
| Permit | Cleared | 8/29/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Williams Homes Inc; Lic. No.: 734097-B | 24911 AVENUE STANFORD SANTA CLARITA, CA 91355 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| ALEXANDER HELFER, (818) 374-4354 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 9/19/2022 | Approved | BRIAN MILLER |
| Bottom/Toe | 10/5/2022 | Partial Approval | BRIAN MILLER |
| SWPPP-Const. Storm Water | 10/5/2022 | Completed | BRIAN MILLER |
| Bottom/Toe | 10/12/2022 | Partial Approval | BRIAN MILLER |
| Rough | 10/14/2022 | Partial Approval | LANNY MERRICK |
| Bottom/Toe | 10/19/2022 | Partial Approval | LANNY MERRICK |
| Deputy Grading | 10/25/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 10/26/2022 | Conditional Approval | LANNY MERRICK |
| Deputy Grading | 10/27/2022 | Conditional Approval | LANNY MERRICK |
| Bottom/Toe | 10/28/2022 | Partial Approval | TIMOTHY POWELL |
| Deputy Grading | 10/28/2022 | Approved | TIMOTHY POWELL |
| Bottom/Toe | 11/4/2022 | Partial Approval | LANNY MERRICK |
| Approved Compaction Report | 1/18/2023 | Approved | BRIAN MILLER |
| Drainage Devices/Catch Basin | 6/2/2023 | Partial Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 6/7/2023 | Partial Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 6/9/2023 | Partial Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 9/6/2023 | Conditional Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 9/7/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 11/8/2023 | Partial Approval | BRIAN MILLER |
| Drainage Devices/Catch Basin | 3/19/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 4/30/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 6/10/2024 | Partial Approval | CHARLES POWELL |
| Drainage Devices/Catch Basin | 8/19/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 8/21/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 2/14/2025 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/19/2025 | Not Ready for Inspection | CHARLES POWELL |
| Approved Compaction Report | 6/10/2025 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 7/2/2025 | Approved | ALEXANDER HELFER |
| Approved Compaction Report | 7/7/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 7/7/2025 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 7/7/2025 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough | 7/7/2025 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Bottom/Toe | 9/9/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Final | 9/9/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough | 9/9/2025 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| SWPPP-Const. Storm Water | 9/9/2025 | Completed | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 9/10/2025 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 10/6/2025 | Partial Approval | MANUEL TEJADA |
| SWPPP-Const. Storm Water | 11/5/2025 | Completed | GERMAN RODRIGUEZ MENDOZA |