2418 S BEVERLY DR 90034
Certificate Information: 2418 S BEVERLY DR 90034
- Application / Permit
- 22030-10000-01379
- Plan Check / Job No.
- B22LA03499
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING FOR (N) SWIMMING POOL/SPA AND RETAINING WALL
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/24/2024
Permit Application Status History
| Submitted | 2/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 3/21/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/22/2022 | SEAN DANG |
| Plan Check Approved | 8/3/2022 | CRYSTEL MAALOUF |
| Issued | 8/4/2022 | APPLICANT |
| Permit Finaled | 4/23/2024 | MATTHEW JENKINS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/3/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 8/3/2022 | CRYSTEL MAALOUF |
Contact Information
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 8/24/2022 | Partial Approval | TIMOTHY POWELL |
| Sub-Drain | 9/2/2022 | Partial Approval | MICHAEL TEMPLE |
| Bottom/Toe | 9/6/2022 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 9/12/2022 | No Access for Inspection | AL GAMBLE |
| Drainage Devices/Catch Basin | 9/14/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 9/14/2022 | Partial Approval | AL GAMBLE |
| Rough | 10/4/2022 | Partial Approval | AL GAMBLE |
| Sub-Drain | 10/12/2022 | Partial Approval | AL GAMBLE |
| Bottom/Toe | 2/16/2023 | Partial Approval | MATTHEW JENKINS |
| Bottom/Toe | 2/23/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/9/2023 | Partial Inspection | MATTHEW JENKINS |
| Excavation | 3/9/2023 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 3/9/2023 | Partial Inspection | MATTHEW JENKINS |
| Bottom/Toe | 3/31/2023 | Corrections Issued | MATTHEW JENKINS |
| Special/Order Compliance | 6/27/2023 | Not Ready for Inspection | VASIL MIHALEV |
| Initial Grading | 7/11/2023 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 8/7/2023 | Partial Inspection | MATTHEW JENKINS |
| Initial Grading | 8/18/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Initial Grading | 11/21/2023 | Partial Approval | CHARLES POWELL |
| Approved Compaction Report | 1/17/2024 | Approved | VASIL MIHALEV |
| Bottom/Toe | 4/23/2024 | Approved | MATTHEW JENKINS |
| Final | 4/23/2024 | Permit Finaled | MATTHEW JENKINS |