19514 W RINALDI ST 91326

Certificate Information: 19514 W RINALDI ST 91326

Application / Permit
22030-10000-01231
Plan Check / Job No.
B22VN00188
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
Site grading for new classroom building under 22010-20000-00064
Permit Issued
Issued on 5/11/2023
Issuing Office
Metro
Current Status
Permit Finaled on 2/4/2025

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Disabled Access Plans Picked Up 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 LAMAR DAVIS
Corrections Issued 2/18/2022 LAMAR DAVIS
Quality Review Completed 3/1/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/7/2022 APPLICANT
Applicant returned to address corrections 4/12/2023 TU HUA
Applicant returned to address corrections 4/21/2023 TU HUA
Plan Check Approved 5/11/2023 TU HUA
Issued 5/11/2023 APPLICANT
Permit Finaled-Status Void 9/13/2024 GERMAN RODRIGUEZ MENDOZA
Re-Activate Permit 12/27/2024 GERMAN RODRIGUEZ MENDOZA
Permit Finaled 2/3/2025 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Address approval Cleared 3/9/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/9/2022 LEE GUILBEAUX
Watercourse Cleared 3/9/2022 LEE GUILBEAUX
Grading Pre-Inspection Cleared 4/21/2023 LAMAR DAVIS
ZA Case Cleared 4/26/2023 DANG NGUYEN
ZA Case Cleared 4/26/2023 DANG NGUYEN
Miscellaneous Cleared 5/10/2023 LAMAR DAVIS

Contact Information

Contractor Do Right Management Inc.; Lic. No.: 737068-B 1220 LINDA LANE      FULLERTON, CA 92831
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

ALEXANDER HELFER, (818) 374-4354 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 5/15/2023 Approved BRIAN MILLER
Bottom/Toe 5/30/2023 Partial Approval BRIAN MILLER
Bottom/Toe 6/7/2023 Partial Approval BRIAN MILLER
Approved Compaction Report 8/3/2023 Approved BRIAN MILLER
Grading Pre-Inspection 11/14/2023 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Bottom/Toe 11/16/2023 Approved ALEXANDER HELFER
Drainage Devices/Catch Basin 11/28/2023 Partial Approval ROBERT PINA
Final 8/19/2024 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough 8/19/2024 Approved GERMAN RODRIGUEZ MENDOZA
Final 9/13/2024 Partial Approval GERMAN RODRIGUEZ MENDOZA
Approved Compaction Report 12/27/2024 Corrections Issued ROBERT PINA
Approved Compaction Report 1/28/2025 Approved MANUEL TEJADA
Final 2/3/2025 Permit Finaled GERMAN RODRIGUEZ MENDOZA