1999 W 3RD ST 90057
Certificate Information: 1999 W 3RD ST 90057
- Application / Permit
- 22030-10000-01182
- Plan Check / Job No.
- B20LA11671
- Group
- Building
- Type
- Grading
- Sub-Type
- Apartment
- Primary Use
- (70) Grading - Hillside
- Work Description
- Board File 220024 APPROVED FOR AN EXPORT OF 1,625 CUBIC YARDS
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/29/2025
Permit Application Status History
| Plan Check Approved | 11/15/2022 | KEVIN MORALES |
| Issued | 12/7/2022 | APPLICANT |
| Permit Finaled | 4/28/2025 | RUSSELL BONVOULOIR |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/24/2022 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 6/24/2022 | KEVIN MORALES |
| Haul Route | Cleared | 10/24/2022 | KARL MUHS |
Contact Information
| Contractor | Benchmark Contractors Inc; Lic. No.: 462263-B | 3330 OCEAN PARK BLVD SANTA MONICA, CA 90405 |
Inspector Information
| RAMAZANALI ALMASI, (213) 482-0398 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 12/23/2022 | Not Ready for Inspection | LANNY MERRICK |
| Excavation | 1/25/2023 | Partial Approval | ALEXANDER HELFER |
| Initial Grading | 2/6/2023 | Approved | LANNY MERRICK |
| Bottom/Toe | 2/9/2023 | Partial Inspection | JONATHAN HOM |
| Initial Grading | 2/22/2023 | Not Ready for Inspection | LANNY MERRICK |
| Initial Grading | 3/6/2023 | Approved | LANNY MERRICK |
| Bottom/Toe | 3/9/2023 | Approved | ALEXANDER HELFER |
| Excavation | 3/9/2023 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 4/20/2023 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 5/12/2023 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 5/15/2023 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 5/16/2023 | Not Ready for Inspection | LANNY MERRICK |
| Fill/Backfill | 5/17/2023 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 5/22/2023 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 5/23/2023 | Not Ready for Inspection | LANNY MERRICK |
| Sub-Drain | 5/30/2023 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 6/1/2023 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 6/6/2023 | Partial Approval | ROBERT HUGHES |
| Sub-Drain | 6/16/2023 | Partial Approval | JONATHAN HOM |
| Drainage Devices/Catch Basin | 6/21/2023 | Partial Inspection | JONATHAN HOM |
| Irrigation/Landscape | 6/21/2023 | Partial Approval | JONATHAN HOM |
| Deputy Other (see comments) | 7/13/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 7/27/2023 | Partial Approval | JONATHAN HOM |
| Sub-Drain | 8/9/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 8/10/2023 | Partial Approval | ALEXANDER HELFER |
| Deputy Other (see comments) | 8/17/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 8/18/2023 | Partial Inspection | RUSSELL BONVOULOIR |
| Sub-Drain | 8/24/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 9/12/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Sub-Drain | 10/23/2023 | Conditional Approval | JONATHAN HOM |
| Excavation | 7/29/2024 | Partial Inspection | JONATHAN HOM |
| Drainage Devices/Catch Basin | 8/30/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Special/Order Compliance | 9/10/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 10/22/2024 | Partial Approval | LANNY MERRICK |
| Sub-Drain | 10/22/2024 | Partial Approval | LANNY MERRICK |
| Fill/Backfill | 12/4/2024 | Partial Inspection | RUSSELL BONVOULOIR |
| Sub-Drain | 12/11/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 1/27/2025 | Corrections Issued | RUSSELL BONVOULOIR |
| Sub-Drain | 2/3/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/21/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Excavation | 2/21/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Drainage Devices/Catch Basin | 2/27/2025 | Partial Approval | RUSSELL BONVOULOIR |
| Approved Compaction Report | 4/23/2025 | Approved | RUSSELL BONVOULOIR |
| Final | 4/28/2025 | Permit Finaled | RUSSELL BONVOULOIR |
| Rough | 4/28/2025 | Order to Comply Issued | RUSSELL BONVOULOIR |