10332 W PENROSE ST 91352

Certificate Information: 10332 W PENROSE ST 91352

Application / Permit
22030-10000-00718
Plan Check / Job No.
B22LA01829
Group
Building
Type
Grading
Sub-Type
Commercial
Primary Use
(70) Grading - Hillside
Work Description
SITE GRADING FOR NEW SOFTBALL FIELD INCLUDING RETAINING WALLS. 1 OF 3
Permit Issued
Issued on 1/14/2025
Issuing Office
Metro
Current Status
Permit Finaled on 5/7/2026

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 QUAN NGHIEM
Corrections Issued 3/15/2022 QUAN NGHIEM
Quality Review Completed 3/18/2022 KEN GILL
Building Plans Picked Up 3/22/2022 APPLICANT
Applicant returned to address corrections 11/21/2024 QUAN NGHIEM
Applicant returned to address corrections 12/3/2024 QUAN NGHIEM
Applicant returned to address corrections 12/4/2024 QUAN NGHIEM
Applicant returned to address corrections 12/5/2024 QUAN NGHIEM
Applicant returned to address corrections 1/10/2025 QUAN NGHIEM
Plan Check Approved 1/14/2025 QUAN NGHIEM
Issued 1/14/2025 APPLICANT
Permit Finaled 5/6/2026 ALEXANDER HELFER

Permit Application Clearance Information

Low Impact Development Cleared 11/4/2024 SARAH YOUSSEF
Excavation more than 5-ft deep Cleared 12/3/2024 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Slyter,, Andrew D.; Lic. No.: C78734 3108 SW REGENCY PARKWAY SUITE 2      BENTONVILLE, AR 72712

Inspector Information

BRIAN MILLER, (818) 374-4359 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Initial Grading 1/17/2025 Approved CHARLES POWELL
Approved Compaction Report 3/5/2025 Corrections Issued MANUEL TEJADA
Rough 3/5/2025 Approved MANUEL TEJADA
Approved Compaction Report 3/25/2025 Corrections Issued MANUEL TEJADA
Approved Compaction Report 4/3/2025 Approved MANUEL TEJADA
Deputy Other (see comments) 4/10/2025 Approved MANUEL TEJADA
Drainage Devices/Catch Basin 4/21/2025 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 4/22/2025 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 5/22/2025 Partial Approval CHARLES POWELL
Sub-Drain 5/22/2025 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 6/2/2025 Partial Approval CHARLES POWELL
Sub-Drain 6/2/2025 Not Ready for Inspection CHARLES POWELL
Drainage Devices/Catch Basin 6/27/2025 Partial Approval CHARLES POWELL
Drainage Devices/Catch Basin 8/26/2025 Partial Approval CHARLES POWELL
Sub-Drain 8/26/2025 Partial Approval CHARLES POWELL
Bottom/Toe 5/6/2026 Approved ALEXANDER HELFER
Final 5/6/2026 Permit Finaled ALEXANDER HELFER