14720 W GREENLEAF ST 91403
Certificate Information: 14720 W GREENLEAF ST 91403
- Application / Permit
- 22030-10000-00512
- Plan Check / Job No.
- B22LA01290
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- GRADING AND REMOVAL AND RECOMPACTION FOR NEW 2-STORY SFD AND 2-STORY ADU 3 OF 3
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Valley
- Current Status
- Issued on 11/10/2022
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 3/4/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 3/8/2022 | SEAN DANG |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Applicant returned to address corrections | 7/20/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/14/2022 | CRYSTEL MAALOUF |
| Issued | 11/10/2022 | APPLICANT |
| Permit Finaled-Status Void | 1/10/2025 | MANUEL TEJADA |
| Re-Activate Permit | 10/17/2025 | MANUEL TEJADA |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/14/2022 | MANUEL TEJADA |
| Grading Pre-Inspection | Cleared | 9/14/2022 | MANUEL TEJADA |
Contact Information
| Contractor | Coast Builders Group Inc; Lic. No.: 872035-B | 6334 CARPENTER AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Moeini,, Soheil; Lic. No.: C84000 | 11022 SANTA MONICA BLVD STE 440 LOS ANGELES, CA 90025 |
Inspector Information
| MATTHEW JENKINS, (818) 374-4357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation | 12/6/2022 | Not Ready for Inspection | LANNY MERRICK |
| Initial Grading | 12/6/2022 | Approved | LANNY MERRICK |
| Deputy Grading | 12/16/2022 | Approved | MANUEL TEJADA |
| Initial Grading | 12/16/2022 | Approved | MANUEL TEJADA |
| Deputy Grading | 12/19/2022 | Approved | MANUEL TEJADA |
| Approved Compaction Report | 2/6/2023 | Approved | BRIAN MILLER |
| Bottom/Toe | 1/10/2025 | Approved | MANUEL TEJADA |
| Final | 1/10/2025 | Partial Approval | MANUEL TEJADA |
| Rough | 1/10/2025 | Approved | MANUEL TEJADA |
| Final | 10/24/2025 | Not Ready for Inspection | MANUEL TEJADA |
| Final | 10/29/2025 | No Access for Inspection | ALEXANDER HELFER |
| Deputy Grading | 10/30/2025 | Approved | ALEXANDER HELFER |
| Excavation | 10/30/2025 | Approved | ALEXANDER HELFER |
| Fill/Backfill | 11/3/2025 | Not Ready for Inspection | ALEXANDER HELFER |
| Approved Compaction Report | 12/4/2025 | Approved | ALEXANDER HELFER |