545 S MAPLETON DR 90024

Certificate Information: 545 S MAPLETON DR 90024

Application / Permit
22030-10000-00221
Plan Check / Job No.
B22LA00566
Group
Building
Type
Grading
Sub-Type
1 or 2 Family Dwelling
Primary Use
(70) Grading - Hillside
Work Description
GRADING FOR NEW POOL SPA AND R&R FOR NEW POOL DECK ON GRADE
Permit Issued
Issued on 6/30/2022
Issuing Office
Metro
Current Status
Permit Finaled on 6/26/2023

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 STARR CHEN
Corrections Issued 1/22/2022 STARR CHEN
Quality Review Completed 1/26/2022 EUGENE BARBEAU
Building Plans Picked Up 1/28/2022 APPLICANT
Applicant returned to address corrections 3/21/2022 STARR CHEN
Applicant returned to address corrections 4/12/2022 STARR CHEN
Applicant returned to address corrections 5/24/2022 STARR CHEN
Plan Check Approved 6/28/2022 STARR CHEN
Issued 6/30/2022 APPLICANT
Permit Finaled 6/23/2023 RUSSELL BONVOULOIR

Permit Application Clearance Information

Address approval Cleared 2/16/2022 JENSON LEE
Eng Process Fee Ord 176,300 Cleared 2/17/2022 JENSON LEE
Grading Pre-Inspection Cleared 6/28/2022 STARR CHEN

Contact Information

Contractor L D L General Contractors Inc; Lic. No.: 856503-B 7216 LITTLER COURT      MOORPARK, CA 93021
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381
Engineer Tran,, Quang Tai; Lic. No.: C70929 355 N LANTANA ST 333      CAMARILLO, CA 93010
Geologist Triebold,, Mark John; Lic. No.: EG1796 6906 QUITO COURT      CAMARILLO, CA 93012
Landscape Architect Rosen,, Joshua Hadly; Lic. No.: LA5610 3932 WADE ST      LOS ANGELES, CA 90066

Inspector Information

JOHNNY MIRANDA, (310) 914-3937 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Bottom/Toe 7/21/2022 Corrections Issued MICHAEL TEMPLE
Excavation 7/21/2022 Partial Inspection MICHAEL TEMPLE
Bottom/Toe 9/28/2022 Partial Inspection AL GAMBLE
Excavation 9/28/2022 Corrections Issued AL GAMBLE
Excavation 10/12/2022 Partial Approval AL GAMBLE
Approved Compaction Report 5/11/2023 Approved MATTHEW JENKINS
Rough 5/12/2023 Corrections Issued MATTHEW JENKINS
Approved Compaction Report 5/25/2023 Approved MATTHEW JENKINS
Bottom/Toe 5/25/2023 Partial Inspection MATTHEW JENKINS
Final 5/25/2023 Partial Inspection MATTHEW JENKINS
Rough 5/25/2023 Partial Inspection MATTHEW JENKINS
Bottom/Toe 6/23/2023 Approved RUSSELL BONVOULOIR
Final 6/23/2023 Permit Finaled RUSSELL BONVOULOIR
Rough 6/23/2023 Approved RUSSELL BONVOULOIR