5042 N ESCOBEDO DR 91364
Certificate Information: 5042 N ESCOBEDO DR 91364
- Application / Permit
- 22030-10000-00161
- Plan Check / Job No.
- B22LA00442
- Group
- Building
- Type
- Grading
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (70) Grading - Hillside
- Work Description
- GRADING WORK FOR RETAINING WALL UNDER 22020-10000-00049. 2 OF 2
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 3/20/2024
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/1/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 2/2/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/4/2022 | APPLICANT |
| Applicant returned to address corrections | 6/17/2022 | FERNANDO FLORES |
| Plan Check Approved | 8/19/2022 | DANIEL SANJUAN |
| Issued | 10/17/2022 | APPLICANT |
| Permit Finaled | 3/19/2024 | ROBERT PINA |
Permit Application Clearance Information
| Hold | Cleared | 3/30/2023 | MARIA VENDIVIL |
Contact Information
| Architect | Nidal, Hamida; Lic. No.: C37969 | , |
| Contractor | Dibara Masonry Llc; Lic. No.: 1002003-B | 3900 W ALAMEDA AVE #1200 BURBANK, CA 91505 |
| Engineer | Esmaili,, Omid; Lic. No.: C87027 | 3395 MICHELSON DR. APARTMENT NO. 3535 IRVINE, CA 92612 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Geologist | Van, Meter, James L.; Lic. No.: EG2031 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 10/24/2022 | Corrections Issued | MANUEL TEJADA |
| Excavation | 4/3/2023 | Not Ready for Inspection | MANUEL TEJADA |
| Initial Grading | 4/3/2023 | Approved | MANUEL TEJADA |
| Initial Grading | 10/31/2023 | Approved | ROBERT PINA |
| Deputy Grading | 11/1/2023 | Conditional Approval | MICHAEL TEMPLE |
| Bottom/Toe | 11/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 11/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Sub-Drain | 11/27/2023 | Partial Approval | ROBERT PINA |
| Bottom/Toe | 12/4/2023 | Partial Approval | ROBERT PINA |
| Sub-Drain | 12/13/2023 | Partial Approval | ROBERT PINA |
| Bottom/Toe | 12/29/2023 | Approved | MANUEL TEJADA |
| Sub-Drain | 1/10/2024 | Partial Approval | ROBERT PINA |
| Approved Compaction Report | 3/12/2024 | Approved | CHARLES POWELL |
| Final | 3/19/2024 | Permit Finaled | ROBERT PINA |
| Rough | 3/19/2024 | Approved | ROBERT PINA |