5949 N VAN NUYS BLVD 91401
Certificate Information: 5949 N VAN NUYS BLVD 91401
- Application / Permit
- 22026-20000-00378
- Plan Check / Job No.
- B22VN17361
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - new
- Work Description
- USA OF LAND PERMIT TO REVISE PORTION OF EXISTING EXTERIOR PARKING LOT USED FOR AUTO DISPLAY OF NEW CARS. NOT REQ'D PARKING AREA.
- Permit Issued
- Issued on 7/6/2023
- Issuing Office
- Valley
- Current Status
- Issued on 7/6/2023
Permit Application Status History
| Submitted | 11/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2022 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/23/2022 | ALEC MOUSAKHANIAN |
| Issued | 7/6/2023 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | United Contractors Inc; Lic. No.: 949005-B | 2174 S MAIN STREET SOUTH SALT LAKE CITY, UT 84115 |
| Engineer | Cunningham,, William; Lic. No.: C80129 | 2745 PARKVIEW DRIVE THOUSAND OAKS, CA 91362 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/31/2023 | Corrections Issued | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 8/31/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Grading Pre-Inspection | 8/31/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Piling/Pier/Caisson | 8/31/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 9/6/2023 | Partial Inspection | ANDREW DORSO |
| Piling/Pier/Caisson | 9/6/2023 | Partial Inspection | ANDREW DORSO |
| Final | 5/24/2024 | Not Ready for Inspection | ROBERT DAVIS |