3159 N LAKE HOLLYWOOD DR 90068
Certificate Information: 3159 N LAKE HOLLYWOOD DR 90068
- Application / Permit
- 22026-10000-00306
- Plan Check / Job No.
- B22LA16233
- Group
- Building
- Type
- Nonbldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- REMOVE AND REPLACE (E) RETAINING WALL. 2 OF 3
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/5/2023
Permit Application Status History
| Submitted | 8/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | KEVIN MORALES |
| Corrections Issued | 9/5/2022 | KEVIN MORALES |
| Quality Review Completed | 9/7/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/7/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 11/30/2022 | KEVIN MORALES |
| Plan Check Approved | 2/16/2023 | KEVIN MORALES |
| Issued | 2/16/2023 | APPLICANT |
| Permit Finaled | 10/4/2023 | ALEXANDER HELFER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/30/2022 | KEVIN MORALES |
| Roof/Waste drainage to street | Cleared | 12/5/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | ABEL CASILLAS |
| Miscellaneous | Cleared | 2/10/2023 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT PINA, (213) 482-0404 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pre-Inspection | 4/4/2023 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 5/11/2023 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 5/16/2023 | Approved | ALEXANDER HELFER |
| Piling/Pier/Caisson | 5/16/2023 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 6/7/2023 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 6/20/2023 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 6/20/2023 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 6/22/2023 | Approved | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 7/19/2023 | Conditional Approval | RUSSELL BONVOULOIR |
| Final | 10/4/2023 | Permit Finaled | ALEXANDER HELFER |