3324 W ROWENA AVE 90027

Certificate Information: 3324 W ROWENA AVE 90027

Application / Permit
22026-10000-00305
Plan Check / Job No.
B22LA17688
Group
Building
Type
Nonbldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(23) Retaining Wall
Work Description
(n) retaining wall max 5' to repair (e) retaining wall per Code Enforcement Citation Case number 697656
Permit Issued
Issued on 1/19/2024
Issuing Office
Metro
Current Status
Permit Finaled on 8/22/2024

Permit Application Status History

Submitted 9/2/2022 APPLICANT
Assigned to Plan Check Engineer 9/8/2022 KELVIN CHUONG
Corrections Issued 9/13/2022 KELVIN CHUONG
Quality Review Completed 9/13/2022 RODOLFO ARIAS
Building Plans Picked Up 10/14/2022 APPLICANT
Applicant returned to address corrections 7/10/2023 KELVIN CHUONG
Applicant returned to address corrections 9/18/2023 KELVIN CHUONG
Plan Check Approved 10/3/2023 KELVIN CHUONG
Issued 1/19/2024 APPLICANT
Permit Finaled 8/21/2024 RUSSELL BONVOULOIR

Permit Application Clearance Information

Construction near power lines Cleared 4/11/2023 RIDWAN HARDY
GPI Written Notices Cleared 7/10/2023 KELVIN CHUONG
Grading Pre-Inspection Cleared 7/10/2023 KELVIN CHUONG

Contact Information

Contractor A M A Construction Services Inc; Lic. No.: 831856-B 536 W ARROW HWY SUITE 201      COVINA, CA 91722
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381

Inspector Information

RAMAZANALI ALMASI, (213) 482-0398 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2024 Approved RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 4/9/2024 Corrections Issued RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 4/25/2024 Not Ready for Inspection RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 4/26/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/29/2024 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 5/8/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 5/9/2024 Conditional Approval RUSSELL BONVOULOIR
Reinforced Masonry Frame 5/17/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 5/20/2024 Approved ALEXANDER HELFER
Deputy Drilled-In Anchors 5/22/2024 Approved RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 5/22/2024 Partial Approval RUSSELL BONVOULOIR
Reinforced Masonry Frame 5/22/2024 Approved RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 5/29/2024 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 6/3/2024 Partial Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 6/3/2024 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/4/2024 Conditional Approval ADAM BURGESS
Deputy Reinf. Concrete 6/5/2024 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/6/2024 Conditional Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 6/7/2024 Approved ALEXANDER HELFER
Deputy Reinf. Concrete 6/10/2024 Conditional Approval RUSSELL BONVOULOIR
Final 8/21/2024 Permit Finaled RUSSELL BONVOULOIR