18585 W VENTURA BLVD 91356

Certificate Information: 18585 W VENTURA BLVD 91356

Application / Permit
22020-30000-02848
Plan Check / Job No.
B22WL04379
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
2 RETAINING WALLS: 3'6" MAX HEIGHT & 93'0" TOTAL LINEAR LENGTH (2 OF 3)
Permit Issued
Issued on 3/12/2025
Issuing Office
Valley
Current Status
Issued on 3/12/2025

Permit Application Status History

Submitted 11/30/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 MARVEL DELACRUZ
Corrections Issued 12/16/2022 MARVEL DELACRUZ
Quality Review Completed 12/22/2022 OMID HEDAYAT
Building Plans Picked Up 1/3/2023 APPLICANT
Disabled Access Plans Picked Up 1/3/2023 APPLICANT
Green Plans Picked Up 1/3/2023 APPLICANT
Applicant returned to address corrections 2/9/2023 MARVEL DELACRUZ
Applicant returned to address corrections 7/25/2023 MARVEL DELACRUZ
Applicant returned to address corrections 8/7/2024 MARVEL DELACRUZ
Applicant returned to address corrections 9/19/2024 MARVEL DELACRUZ
Applicant returned to address corrections 12/12/2024 MARVEL DELACRUZ
Applicant returned to address corrections 1/22/2025 MARVEL DELACRUZ
Plan Check Approved 3/12/2025 MARVEL DELACRUZ
Issued 3/12/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 3/6/2025 MAIRA SANCHEZ
ZI Cleared 3/6/2025 MAIRA SANCHEZ

Contact Information

Contractor Harvey Usa Llc; Lic. No.: 866177-B 9455 RIDGEHAVEN COURT STE 200      SAN DIEGO, CA 92123
Engineer Blankfard,, David Gordon; Lic. No.: C78801 1805 CATES CREEK PKWY      HILLSBOROUGH, NC 27278
Engineer Morgan,, Joshua Ryan; Lic. No.: C86032 1043 12TH STREET 4      SANTA MONICA, CA 90403

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/2/2025 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 9/3/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/5/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 9/18/2025 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 9/19/2025 Conditional Approval BRIAN KELLY
Masonry Wall/Backfill 9/22/2025 Partial Approval BRIAN KELLY
Reinforced Masonry Frame 9/22/2025 Partial Approval BRIAN KELLY
Deputy Reinf. Masonry 9/23/2025 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 12/12/2025 Partial Inspection BRIAN KELLY
Masonry Wall/Backfill 12/22/2025 Partial Approval BRIAN KELLY
Deputy Reinf. Masonry 12/23/2025 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 1/16/2026 Conditional Approval BRIAN KELLY
Excavation/Setback/Form/Re-Bar 1/16/2026 Partial Approval BRIAN KELLY
Final 3/9/2026 Partial Inspection BRIAN KELLY