12530 W CLOUD LANE 90049
Certificate Information: 12530 W CLOUD LANE 90049
- Application / Permit
- 22020-30000-02344
- Plan Check / Job No.
- B22WL03709
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- New irregular shaped elevated deck (71'-10" x 25'-3") attached to the house and new detached elevated deck (6'-2" x 5'-5") at rear of the lot
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 5/15/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2022 | REZA HAGHIGHAT |
| Corrections Issued | 10/17/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 10/25/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/15/2022 | APPLICANT |
| Applicant returned to address corrections | 12/7/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 11/30/2023 | REZA HAGHIGHAT |
| Plan Check Approved | 5/29/2024 | REZA HAGHIGHAT |
| Issued | 9/30/2024 | APPLICANT |
| CofO in Progress | 5/15/2026 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/12/2023 | REZA HAGHIGHAT |
| Low Impact Development | Cleared | 5/14/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/14/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | ANTHONY MAINEZ |
Contact Information
| Contractor | Trade Construction Services Inc; Lic. No.: 1062967-B | 3525 OLD CONEJO RD STE #102 NEWBURY PARK, CA 93120 |
| Engineer | Mina,, Joseph; Lic. No.: C53465 | 7247 DARNOCH WY WEST HILLS, CA 91307 |
| Geologist | Norton,, Steven A; Lic. No.: GEO9875 | 1417 ARMACOST AVE #10 LOS ANGELES, CA 90025 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/28/2024 | Partial Inspection | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 12/12/2024 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 12/19/2024 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 12/19/2024 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 2/26/2025 | Conditional Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/24/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 5/20/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Approved | BOBBY KEY |
| Wood Frame | 8/13/2025 | Approved | BOBBY KEY |
| Final | 5/15/2026 | OK to Issue CofO | KEVIN SARGSYAN |