1529 N SKYLARK LANE 90069
Certificate Information: 1529 N SKYLARK LANE 90069
- Application / Permit
- 22020-30000-01423
- Plan Check / Job No.
- B22WL02442
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Temp. shoring for S.F.D., ALQ, retaining walls *** 2 of 2 ***
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Metro
- Current Status
- Issued on 9/28/2022
Permit Application Status History
| Submitted | 6/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | KAVIAN REFAHI |
| Corrections Issued | 7/2/2022 | KAVIAN REFAHI |
| Quality Review Completed | 7/7/2022 | TARIK SAOUD |
| Plan Check Approved | 9/22/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 9/22/2022 | APPLICANT |
| Issued | 9/28/2022 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/1/2022 | KAVIAN REFAHI |
Contact Information
| Contractor | Jones Builders Group Inc; Lic. No.: 904861-B | 23823 MALIBU RD 50-375 MALIBU, CA 90265 |
| Engineer | Daneshfar, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
| Geologist | Feffer, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 1/25/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 1/26/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 1/27/2023 | Conditional Approval | RAUL BARAJAS |
| Piling/Pier/Caisson | 1/31/2023 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 1/31/2023 | Approved | RAUL BARAJAS |
| Piling/Pier/Caisson | 2/2/2023 | Partial Approval | RAUL BARAJAS |
| Pre-Inspection | 2/2/2023 | Partial Approval | RAUL BARAJAS |
| Grading Pre-Inspection | 8/11/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Posting Pre-Inspection | 8/11/2023 | Partial Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 12/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Reinforced Concrete Frame | 12/12/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |