3055 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3055 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 22020-30000-00869
- Plan Check / Job No.
- B22WL01498
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (n) retaining wall on piles
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 7/19/2024
Permit Application Status History
| Submitted | 4/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2022 | TARIK SAOUD |
| Corrections Issued | 4/25/2022 | TARIK SAOUD |
| Quality Review Completed | 4/26/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 6/30/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 9/6/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 10/14/2022 | KAVIAN REFAHI |
| Applicant returned to address corrections | 10/17/2022 | KAVIAN REFAHI |
| Building Plans Picked Up | 10/17/2022 | APPLICANT |
| Plan Check Approved | 11/23/2022 | KAVIAN REFAHI |
| Plan Check Approved | 1/3/2023 | KAVIAN REFAHI |
| Issued | 1/3/2023 | APPLICANT |
| Permit Finaled | 7/18/2024 | MATTHEW JENKINS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/14/2022 | MARTIN FRAGOSO |
| Landscape for retaining wall | Cleared | 7/13/2022 | JASON CHAN |
| Construction within easement | Cleared | 9/27/2022 | WALTER RAMIREZ |
| Excavation more than 5-ft deep | Cleared | 11/23/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26940 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Haddad,, Raymond Mounir; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Reinforced Concrete Frame | 5/23/2023 | Partial Approval | RUSSELL BONVOULOIR |
| Final | 7/18/2024 | Permit Finaled | MATTHEW JENKINS |