506 N EVERGREEN AVE 90033

Certificate Information: 506 N EVERGREEN AVE 90033

Application / Permit
22020-30000-00329
Plan Check / Job No.
B22WL00518
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
new 7-site retaining walls to create pathways
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
Permit Finaled on 12/22/2022

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 TARIK SAOUD
Corrections Issued 2/20/2022 TARIK SAOUD
Quality Review Completed 3/7/2022 CHIHARU SUZUKI
Disabled Access Plans Picked Up 3/8/2022 APPLICANT
Applicant returned to address corrections 4/20/2022 TARIK SAOUD
Plan Check Approved 7/20/2022 TARIK SAOUD
Building Plans Picked Up 7/20/2022 APPLICANT
Issued 7/27/2022 APPLICANT
Permit Finaled 12/21/2022 RAFAEL CORTES

Permit Application Clearance Information

Low Impact Development Cleared 6/28/2022 TA ANH

Contact Information

Contractor Lv Construction Inc; Lic. No.: 1043604-B 1768 MARY ROAD      ACTON, CA 93510
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Larocca,, Francis; Lic. No.: C75121 2008A BELMONT LANE      REDONDO BEACH, CA 90278
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007
Engineer Zahn,, Michael; Lic. No.: S5054 9119 HARGIS STREET      LOS ANGELES, CA 90034

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/25/2022 Partial Approval ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 8/25/2022 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 8/30/2022 Approved ROBERT HUGHES
Excavation/Setback/Form/Re-Bar 9/16/2022 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/21/2022 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 9/27/2022 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 9/28/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/7/2022 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 10/7/2022 Partial Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/13/2022 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 10/17/2022 Partial Approval MARK FERRARI
Footing/Foundation/Slab 10/17/2022 Partial Approval MARK FERRARI
Masonry Wall/Backfill 10/17/2022 Partial Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 10/25/2022 Partial Inspection MARK FERRARI
Footing/Foundation/Slab 10/26/2022 Partial Approval KATY RAMIREZ
Final 12/21/2022 Permit Finaled RAFAEL CORTES