3475 S BEETHOVEN ST 90066
Certificate Information: 3475 S BEETHOVEN ST 90066
- Application / Permit
- 22020-20000-03240
- Plan Check / Job No.
- B22VN19094
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) 5FT HIGH MAX (191LF) RETAINING WALL PER ENG'R DESIGN
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/10/2023
Permit Application Status History
| Submitted | 12/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/24/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/25/2023 | STEVEN KIM |
| Building Plans Picked Up | 1/27/2023 | APPLICANT |
| Applicant returned to address corrections | 4/7/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 6/29/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/29/2023 | NILOOFAR MEHRAIN |
| Issued | 6/29/2023 | APPLICANT |
| Permit Finaled | 10/10/2023 | MATTHEW JENKINS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/8/2023 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2023 | AHMED AMARRAGY |
Contact Information
| Contractor | Nfq Builder Inc; Lic. No.: 1067990-B | 2110 ARTESIA BLVD #561 REDONDO BEACH, CA 90278 |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
| Engineer | Mao,, Yuqiao; Lic. No.: C90108 | 136 LOST HILLS IRVINE, CA 92618 |
Inspector Information
| JOHNNY MIRANDA, (310) 914-3937 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 7/18/2023 | Corrections Issued | MATTHEW JENKINS |
| Footing/Foundation/Slab | 7/20/2023 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 7/21/2023 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 7/24/2023 | Partial Approval | MATTHEW JENKINS |
| Footing/Foundation/Slab | 7/27/2023 | Partial Approval | MATTHEW JENKINS |
| Final | 8/11/2023 | Corrections Issued | MATTHEW JENKINS |
| Final | 8/22/2023 | Partial Inspection | MATTHEW JENKINS |
| Final | 9/19/2023 | Not Ready for Inspection | MATTHEW JENKINS |
| Final | 10/10/2023 | Permit Finaled | MATTHEW JENKINS |