833 N MARTEL AVE 90046
Certificate Information: 833 N MARTEL AVE 90046
- Application / Permit
- 22020-20000-02936
- Plan Check / Job No.
- B22VN18208
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Permanent)
- Work Description
- SHORING FOR NEW APARTMENT BUILDING
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Valley
- Current Status
- Issued on 9/14/2023
Permit Application Status History
| Submitted | 12/12/2022 | APPLICANT |
| Green Plans Picked Up | 1/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2023 | RARES BODEA |
| Corrections Issued | 1/30/2023 | RARES BODEA |
| Quality Review Completed | 1/31/2023 | STEVEN KIM |
| Building Plans Picked Up | 2/3/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 2/9/2023 | APPLICANT |
| Applicant returned to address corrections | 5/1/2023 | RARES BODEA |
| Applicant returned to address corrections | 6/21/2023 | RARES BODEA |
| Plan Check Approved | 9/14/2023 | RARES BODEA |
| Issued | 9/14/2023 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/26/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2023 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | CELINA MORENO |
Contact Information
| Contractor | La Rocca Design; Lic. No.: 779452-B | 921 SOUTH SPAULDING AVENUE LOS ANGELES, CA 90046 |
| Engineer | Le,, Thang Huu; Lic. No.: C63174 | 507 MAGELLAN RD ARCADIA, CA 91007 |
| Engineer | Zahn,, Michael; Lic. No.: S5054 | 9119 HARGIS STREET LOS ANGELES, CA 90034 |
Inspector Information
| MARTIN TAVITIAN, (213) 482-7357 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/7/2023 | Partial Approval | ALFREDO LOPEZ |
| Piling/Pier/Caisson | 12/18/2023 | Partial Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 12/18/2023 | Partial Inspection | ALFREDO LOPEZ |
| Deputy Reinf. Concrete | 12/19/2023 | No Access for Inspection | MICHAEL ROSENBERG |
| Deputy Grading | 1/2/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Grading | 1/3/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/8/2024 | Conditional Approval | ALFREDO LOPEZ |
| Piling/Pier/Caisson | 1/8/2024 | Partial Approval | ALFREDO LOPEZ |
| Deputy Grading | 1/10/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 1/23/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 5/15/2024 | No Access for Inspection | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 5/16/2024 | Approved | JACOB MYERS |