6007 N RESEDA BLVD 91356
Certificate Information: 6007 N RESEDA BLVD 91356
- Application / Permit
- 22020-20000-02695
- Plan Check / Job No.
- B22VN16681
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePLAN PROPOSED 10' X 16' EQUIPMENT PAD ENCLOSURE W/ 6'-6" HIGH BLOCK WALLS. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | RAPHAEL ROSAS |
| Corrections Issued | 12/27/2022 | RAPHAEL ROSAS |
| Quality Review Completed | 12/28/2022 | STEVEN KIM |
| Applicant returned to address corrections | 4/20/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 5/6/2025 | RAPHAEL ROSAS |
| Issued | 5/13/2025 | APPLICANT |
| Re-Activate Permit | 6/25/2025 | BRIAN KELLY |
| Permit Expired-Status Void | 6/25/2025 | BRIAN KELLY |
| CofO in Progress | 6/30/2025 | BRIAN KELLY |
| Permit Finaled | 7/1/2025 | JEFFREY DURAN |
| CofO Issued | 7/1/2025 | JEFFREY DURAN |
| Permit Finaled | 7/1/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/1/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 3/1/2023 | DALIA MOKAYED |
| ZA Case | Cleared | 3/1/2023 | DALIA MOKAYED |
| Miscellaneous | Cleared | 12/6/2023 | MELITA EVANS |
| Miscellaneous | Cleared | 4/21/2025 | MELITA EVANS |
| Miscellaneous | Cleared | 4/21/2025 | MELITA EVANS |
Contact Information
| Contractor | General Dynamics Information Technology Inc; Lic. No.: 923979-B | , |
| Engineer | Leeper,, Michael; Lic. No.: NA83930 | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Not Ready for Inspection | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 5/30/2025 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 5/30/2025 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/4/2025 | Conditional Approval | BRIAN KELLY |
| Masonry Wall/Backfill | 6/4/2025 | Approved | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/20/2025 | Conditional Approval | BRIAN KELLY |
| Final | 6/24/2025 | OK to Issue CofO | BRIAN KELLY |