20144 W MARLOW LANE 91326
Certificate Information: 20144 W MARLOW LANE 91326
- Application / Permit
- 22020-20000-02260
- Plan Check / Job No.
- B22VN14238
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Fence Wall
- Work Description
- PROPOSE 6' HIGH FENCE WALL (ALONG NORTH PROPERTY LINE) AT 84.5' IN LENGTH AND FENCE/RETAINING WALL(ALONG SOUTH PROPERTY LINE) AT 75.4' IN LENGTH _ PER PROTO WALL II_ PER LA CITY STANDARD PLAN #520.
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/11/2023
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | DAWN MC NULTY |
| Corrections Issued | 10/13/2022 | DAWN MC NULTY |
| Quality Review Completed | 10/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 11/14/2022 | APPLICANT |
| Applicant returned to address corrections | 3/1/2023 | DAWN MC NULTY |
| Applicant returned to address corrections | 3/2/2023 | DAWN MC NULTY |
| Plan Check Approved | 5/5/2023 | DAWN MC NULTY |
| Issued | 5/5/2023 | APPLICANT |
| Permit Finaled | 9/8/2023 | HENRY KIM |
Permit Application Clearance Information
| "T" removal | Cleared | 11/9/2022 | BRENNEN OBETO |
| CPC | Cleared | 11/9/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 11/9/2022 | BRENNEN OBETO |
| Miscellaneous | Cleared | 11/9/2022 | BRENNEN OBETO |
| Specific Plan | Cleared | 11/9/2022 | BRENNEN OBETO |
| Tract Map conditions | Cleared | 11/9/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 11/9/2022 | BRENNEN OBETO |
| ZA Case | Cleared | 11/9/2022 | BRENNEN OBETO |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 1140 VIRGINIA DR ATTN: TOLL BROTHERS - TAGGERT/LEGAL FORT WASHINGTON, PA 19034 |
| Engineer | Majeroni,, Todd Edward; Lic. No.: C69616 | 9080 W CHEYENNE AVE STE 120 LAS VEGAS, NV 89129 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/7/2023 | Approved | HENRY KIM |
| Deputy Drilled-In Anchors | 8/16/2023 | Conditional Approval | HENRY KIM |
| Final | 9/8/2023 | Permit Finaled | HENRY KIM |