7250 N LAUREL CANYON BLVD 91605
Certificate Information: 7250 N LAUREL CANYON BLVD 91605
- Application / Permit
- 22020-20000-02027
- Plan Check / Job No.
- B22VN13147
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- EPLAN Install a 250KW Diesel Generator, Install Housekeeping Pad for Generator.
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2022 | ZAW HAN |
| Corrections Issued | 9/4/2022 | ZAW HAN |
| Applicant returned to address corrections | 4/21/2023 | ZAW HAN |
| Plan Check Approved | 5/2/2023 | ZAW HAN |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 6/25/2024 | ANDREW DORSO |
| Permit Finaled | 7/5/2024 | JEFFREY DURAN |
| CofO Issued | 7/5/2024 | JEFFREY DURAN |
| Permit Finaled | 7/5/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/5/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | West Coast Lighting & Energy Inc; Lic. No.: 764981-B | , |
| Engineer | Flanagan,, Joseph Neil; Lic. No.: C58349 | 930 CENTRAL KANSAS CITY, MO 64105 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Footing/Foundation/Slab | 7/13/2023 | Not Ready for Inspection | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 7/17/2023 | Approved | ROBERT DAVIS |
| Footing/Foundation/Slab | 7/17/2023 | Approved | ROBERT DAVIS |
| Deputy Reinf. Concrete | 7/18/2023 | Conditional Approval | ROBERT DAVIS |
| Final | 6/10/2024 | OK to Issue CofO | ANDREW DORSO |