20441 W ROBERT PL 91364
Certificate Information: 20441 W ROBERT PL 91364
- Application / Permit
- 22020-20000-01968
- Plan Check / Job No.
- B22VN12037
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW 204 LF X 6 FT HIGH RETAINING WALL (6 FT HIGH MAX ABOVE NATURAL GRADE IN THE REQUIRED REAR AND SIDE YARD, 3,5 FT HIGH MAX ABOVE NATURAL GRADE IN THE REQUIRED FRONT YARD), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- Permit Finaled on 4/16/2024
Permit Application Status History
| Submitted | 8/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | RARES BODEA |
| Corrections Issued | 8/22/2022 | RARES BODEA |
| Quality Review Completed | 8/25/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/30/2022 | APPLICANT |
| Applicant returned to address corrections | 9/28/2022 | RARES BODEA |
| Applicant returned to address corrections | 12/9/2022 | RARES BODEA |
| Plan Check Approved | 12/19/2022 | RARES BODEA |
| Issued | 12/19/2022 | APPLICANT |
| Permit Finaled | 4/16/2024 | ROBERT PINA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 9/20/2022 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 9/28/2022 | RARES BODEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2023 | Corrections Issued | MANUEL TEJADA |
| Footing/Foundation/Slab | 1/26/2023 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Approved | ROBERT PINA |
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | ROBERT PINA |
| Piling/Pier/Caisson | 2/1/2023 | Partial Approval | ROBERT PINA |
| Excavation/Setback/Form/Re-Bar | 2/9/2023 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 2/9/2023 | Partial Inspection | ALEXANDER HELFER |
| Masonry Wall/Backfill | 4/18/2023 | Partial Approval | ALEXANDER HELFER |
| Posting Pre-Inspection | 7/27/2023 | Partial Inspection | MICHAEL TEMPLE |
| Special/Order Compliance | 7/31/2023 | Corrections Issued | MICHAEL TEMPLE |
| Pre-Inspection | 9/11/2023 | Partial Inspection | MICHAEL TEMPLE |
| Final | 4/16/2024 | Permit Finaled | ROBERT PINA |