600 N SEPULVEDA BLVD 90049

Certificate Information: 600 N SEPULVEDA BLVD 90049

Application / Permit
22020-20000-01939
Plan Check / Job No.
B21VN01565
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Fence Wall
Work Description
New 6'-0" high block walls enclosing parking (lengths of 70'-0" and 48'-6"), New 12'-2" high concrete wall enclosing the courtyard length of 57'-8" , New 12'-2" high concrete wall enclosing front courtyard length of 61'-6", ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/18/2022
Issuing Office
Current Status
Permit Finaled on 4/16/2025

Permit Application Status History

Submitted 2/12/2021 APPLICANT
Disabled Access Plans Picked Up 2/26/2021 APPLICANT
Assigned to Plan Check Engineer 3/4/2021 ALYSSA N NARCISO
Green Plans Picked Up 3/8/2021 APPLICANT
Corrections Issued 3/12/2021 ALYSSA N NARCISO
Quality Review Completed 3/16/2021 STEVEN KIM
Applicant returned to address corrections 11/10/2021 RARES BODEA
Applicant returned to address corrections 5/17/2022 RARES BODEA
Applicant returned to address corrections 8/9/2022 RARES BODEA
Plan Check Approved 8/17/2022 RARES BODEA
Issued 8/18/2022 APPLICANT
Permit Finaled 4/15/2025 FARHAD DADBIN

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Goodman,, Benjamin Isaac; Lic. No.: C35193 1952 HILLCREST DRIVE      LOS ANGELES, CA 90016
Contractor Machina Group Inc The; Lic. No.: 957436-B 5758 BURNET AVE      VAN NUYS, CA 91411
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/17/2023 Approved DERRICK SPENCER
Deputy Reinf. Concrete 1/18/2023 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 1/19/2023 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 1/20/2023 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Concrete 2/22/2023 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 2/22/2023 Partial Approval PAUL DAVIDSON
Footing/Foundation/Slab 2/22/2023 Partial Approval PAUL DAVIDSON
Deputy Reinf. Concrete 2/23/2023 Conditional Approval PAUL DAVIDSON
Deputy Reinf. Masonry 4/3/2023 Conditional Approval PAUL DAVIDSON
Masonry Wall/Backfill 4/3/2023 Partial Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 5/2/2023 Partial Approval PAUL DAVIDSON
Masonry Wall/Backfill 5/2/2023 Partial Approval PAUL DAVIDSON
Deputy Reinf. Masonry 5/11/2023 Conditional Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 5/11/2023 Partial Approval PAUL DAVIDSON
Reinforced Masonry Frame 5/11/2023 Partial Approval PAUL DAVIDSON
Excavation/Setback/Form/Re-Bar 6/13/2023 Partial Approval PAUL DAVIDSON
Masonry Wall/Backfill 6/22/2023 Partial Approval PAUL DAVIDSON
Masonry Wall/Backfill 10/2/2023 Partial Approval PAUL DAVIDSON
Final 4/15/2025 Permit Finaled FARHAD DADBIN