19245 W SANTA RITA ST 91356
Certificate Information: 19245 W SANTA RITA ST 91356
- Application / Permit
- 22020-20000-01869
- Plan Check / Job No.
- B22VN12208
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALLS (144.41 LINEAR FEET, MAX HEIGHT OF 6')
- Permit Issued
- Issued on 11/29/2022
- Issuing Office
- Current Status
- Permit Finaled on 7/17/2024
Permit Application Status History
| Submitted | 8/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/25/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Plan Check Approved | 11/29/2022 | SELLA BENYAMIN |
| Issued | 11/29/2022 | APPLICANT |
| Permit Finaled | 7/16/2024 | GERMAN RODRIGUEZ MENDOZA |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/27/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 11/1/2022 | JOSE DUARTE-DIAZ |
| Public Works-Open Permits | Cleared | 11/1/2022 | JOSE DUARTE-DIAZ |
| Public Works-Sewers | Cleared | 11/1/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MANUEL TEJADA, (818) 374-4339 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/16/2022 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Corrections Issued | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Partial Inspection | ALEXANDER HELFER |
| Excavation/Setback/Form/Re-Bar | 2/10/2023 | Partial Inspection | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/9/2023 | Partial Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/14/2023 | Conditional Approval | MANUEL TEJADA |
| Footing/Foundation/Slab | 8/14/2023 | Conditional Approval | MANUEL TEJADA |
| Masonry Wall/Backfill | 8/14/2023 | Conditional Approval | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Not Ready for Inspection | MANUEL TEJADA |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Corrections Issued | ROBERT PINA |
| Footing/Foundation/Slab | 8/24/2023 | Not Ready for Inspection | ROBERT PINA |
| Reinforced Concrete Frame | 8/25/2023 | Partial Approval | ROBERT PINA |
| Masonry Wall/Backfill | 9/7/2023 | Partial Approval | ROBERT PINA |
| Masonry Wall/Backfill | 9/12/2023 | Partial Approval | ROBERT PINA |
| Special/Order Compliance | 12/21/2023 | Partial Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 2/28/2024 | Not Ready for Inspection | CHARLES POWELL |
| Final | 7/8/2024 | Not Ready for Inspection | CHARLES POWELL |
| Final | 7/16/2024 | Permit Finaled | GERMAN RODRIGUEZ MENDOZA |