19245 W SANTA RITA ST 91356

Certificate Information: 19245 W SANTA RITA ST 91356

Application / Permit
22020-20000-01869
Plan Check / Job No.
B22VN12208
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALLS (144.41 LINEAR FEET, MAX HEIGHT OF 6')
Permit Issued
Issued on 11/29/2022
Issuing Office
Current Status
Permit Finaled on 7/17/2024

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 SELLA BENYAMIN
Corrections Issued 8/25/2022 SELLA BENYAMIN
Quality Review Completed 8/30/2022 STEVEN KIM
Plan Check Approved 11/29/2022 SELLA BENYAMIN
Issued 11/29/2022 APPLICANT
Permit Finaled 7/16/2024 GERMAN RODRIGUEZ MENDOZA

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/27/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/1/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 11/1/2022 JOSE DUARTE-DIAZ
Public Works-Open Permits Cleared 11/1/2022 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 11/1/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MANUEL TEJADA, (818) 374-4339 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 12/16/2022 Corrections Issued MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 12/19/2022 Corrections Issued ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Inspection ALEXANDER HELFER
Excavation/Setback/Form/Re-Bar 2/10/2023 Partial Inspection MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 8/9/2023 Partial Approval MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 8/14/2023 Conditional Approval MANUEL TEJADA
Footing/Foundation/Slab 8/14/2023 Conditional Approval MANUEL TEJADA
Masonry Wall/Backfill 8/14/2023 Conditional Approval MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 8/22/2023 Not Ready for Inspection MANUEL TEJADA
Excavation/Setback/Form/Re-Bar 8/24/2023 Corrections Issued ROBERT PINA
Footing/Foundation/Slab 8/24/2023 Not Ready for Inspection ROBERT PINA
Reinforced Concrete Frame 8/25/2023 Partial Approval ROBERT PINA
Masonry Wall/Backfill 9/7/2023 Partial Approval ROBERT PINA
Masonry Wall/Backfill 9/12/2023 Partial Approval ROBERT PINA
Special/Order Compliance 12/21/2023 Partial Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 2/28/2024 Not Ready for Inspection CHARLES POWELL
Final 7/8/2024 Not Ready for Inspection CHARLES POWELL
Final 7/16/2024 Permit Finaled GERMAN RODRIGUEZ MENDOZA