11668 W SHERMAN WAY 91605

Certificate Information: 11668 W SHERMAN WAY 91605

Application / Permit
22020-20000-01865
Plan Check / Job No.
B22VN12177
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(61) Use of Land
Work Description
ePlan: New slabs for mechanical equipment structure and generator. Mechanical equipment structure under separate permit.
Permit Issued
Issued on 1/19/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2022 APPLICANT
Assigned to Plan Check Engineer 8/18/2022 ERIC WONG
Corrections Issued 8/20/2022 ERIC WONG
Quality Review Completed 8/26/2022 PETER KIM
Applicant returned to address corrections 11/3/2022 ERIC WONG
Applicant returned to address corrections 12/6/2022 ERIC WONG
Plan Check Approved 1/19/2023 ERIC WONG
Issued 1/19/2023 APPLICANT
Permit Finaled 7/9/2025 RICKEY JACKSON
CofO Issued 7/9/2025 RICKEY JACKSON
Permit Finaled 7/9/2025 RICKEY JACKSON

Permit Application Clearance Information

DAS Clearance Cleared 9/1/2022 ERIC WONG
Prkng lot landscape/Water mgmt Cleared 9/7/2022 RUBEN VASQUEZ
Low Impact Development Cleared 1/5/2023 AMMAR ELTAWIL

Contact Information

Architect Archer,, Mary Lou; Lic. No.: C22309 15735 NORDHOFF ST #29      NORTH HILLS, CA 913433120
Contractor Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B 4175 E LA PALMA AVE STE 200      ANAHEIM, CA 92807
Engineer Roi,, Jeffrey Steven; Lic. No.: S5849 300 S GRAND AVE, SUITE 3850      LOS ANGELES, CA 90071

Inspector Information

JEFFREY FULTON, (818) 374-1132 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 4/3/2023 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 4/3/2023 Conditional Approval ROBERT DAVIS
Pre-Inspection 4/4/2023 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 8/22/2023 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/2/2023 Partial Inspection ROBERT DAVIS
Deputy Reinf. Concrete 10/11/2023 Approved ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/11/2023 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 10/11/2023 Partial Approval ROBERT DAVIS
Pre-Inspection 10/11/2023 Approved ROBERT DAVIS
Pre-Inspection 10/11/2023 Off-Hour Fees Due
Pre-Inspection 10/17/2023 Partial Inspection ROBERT DAVIS
Structural Steel Frame 10/17/2023 Partial Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 10/24/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 10/24/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 10/24/2023 Partial Inspection DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 10/26/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 10/26/2023 Partial Approval CAMERON CHABAN
Pre-Inspection 10/26/2023 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 11/3/2023 Approved ROBERT DAVIS
Pre-Inspection 11/3/2023 Approved ROBERT DAVIS
Deputy Reinf. Concrete 11/6/2023 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 11/8/2023 Conditional Approval ROBERT DAVIS
Deputy Grading 11/9/2023 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/16/2023 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 11/16/2023 Partial Approval ROBERT DAVIS
Pre-Inspection 11/16/2023 Approved ROBERT DAVIS
Deputy Drilled-In Anchors 12/5/2023 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/12/2023 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/12/2023 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 12/12/2023 Not Ready for Inspection ROBERT DAVIS
Pre-Inspection 12/12/2023 No Access for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/13/2023 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 12/13/2023 Partial Inspection ANDREW DORSO
Pre-Inspection 12/13/2023 Partial Inspection ANDREW DORSO
Deputy Drilled-In Anchors 12/14/2023 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 12/14/2023 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 12/29/2023 Conditional Approval CAMERON CHABAN
Footing/Foundation/Slab 12/29/2023 Partial Approval CAMERON CHABAN
Pre-Inspection 12/29/2023 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 1/17/2024 Approved ROBERT DAVIS
Footing/Foundation/Slab 1/17/2024 Partial Approval ROBERT DAVIS
Pre-Inspection 1/17/2024 Partial Approval ROBERT DAVIS
Deputy Grading 2/26/2024 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 2/29/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/5/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/6/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/7/2024 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 3/8/2024 Conditional Approval ROBERT DAVIS
Deputy Drilled-In Anchors 3/13/2024 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 3/13/2024 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 3/13/2024 Partial Approval ROBERT DAVIS
Piling/Pier/Caisson 3/13/2024 Partial Approval ROBERT DAVIS
Pre-Inspection 3/13/2024 Approved ROBERT DAVIS
Deputy Steel/Welding 3/15/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/18/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/19/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/20/2024 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 3/21/2024 Conditional Approval KENNETH ROBERTS
Excavation/Setback/Form/Re-Bar 3/21/2024 Partial Approval KENNETH ROBERTS
Footing/Foundation/Slab 3/21/2024 Partial Approval KENNETH ROBERTS
Piling/Pier/Caisson 3/21/2024 Partial Approval KENNETH ROBERTS
Pre-Inspection 3/21/2024 Approved KENNETH ROBERTS
Special/Order Compliance 4/30/2024 Partial Inspection ANDREW DORSO
Deputy Grading 8/16/2024 Conditional Approval CAMERON CHABAN
Deputy Grading 8/20/2024 Conditional Approval STEVEN LEVITT
Deputy Reinf. Concrete 8/20/2024 Conditional Approval STEVEN LEVITT
Deputy Grading 8/21/2024 Conditional Approval STEVEN LEVITT
Deputy Grading 8/22/2024 Conditional Approval STEVEN LEVITT
Deputy Grading 8/23/2024 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 8/23/2024 Approved JOHN KITCKO
Final 9/19/2024 Conditional Approval STEVEN LEVITT
Final 2/6/2025 Partial Approval STEVEN LEVITT