1682 N SAN ONOFRE DR 90272
Certificate Information: 1682 N SAN ONOFRE DR 90272
- Application / Permit
- 22020-20000-01678
- Plan Check / Job No.
- B22VN11152
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- NEW RETAINING WALL 10 FT HIGH X 32.66 LN FT , NEW RET WALL 10 FT HIGH X 130 FT LONG RETAINING WALL (3.5 FT HIGH MAX ABOIVE NATURAL GRADE IN THE REQUIRED FRONT YARD, 6 FT MAX ABOVE NATURAL GRADE IN THE REQUIRED SIDE YARD), ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/24/2025
Permit Application Status History
| Submitted | 7/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | RARES BODEA |
| Plans on Hold | 8/8/2022 | RARES BODEA |
| Hold Released | 8/10/2022 | RARES BODEA |
| Corrections Issued | 8/10/2022 | RARES BODEA |
| Quality Review Completed | 8/12/2022 | STEVEN KIM |
| Building Plans Picked Up | 8/16/2022 | APPLICANT |
| Applicant returned to address corrections | 9/14/2022 | RARES BODEA |
| Applicant returned to address corrections | 2/3/2023 | RARES BODEA |
| Plan Check Approved | 2/15/2023 | RARES BODEA |
| Issued | 3/8/2023 | APPLICANT |
| Permit Finaled | 4/24/2025 | JOHNNY MIRANDA |
Permit Application Clearance Information
| Landscape for retaining wall | Cleared | 1/18/2023 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 1/31/2023 | JENSON LEE |
| Grading Pre-Inspection | Cleared | 2/3/2023 | RARES BODEA |
| Construction near power lines | Cleared | 2/13/2023 | RIDWAN HARDY |
| Construction near power lines | Cleared | 2/13/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Ortam Construction Inc; Lic. No.: 880225-B | 4500 PARK GRANADA #202 CALABASAS, CA 91302 |
Inspector Information
| RAMAZANALI ALMASI, (310) 914-3899 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 5/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 5/10/2023 | Approved | VASIL MIHALEV |
| Deputy Other (see comments) | 5/11/2023 | Conditional Approval | VASIL MIHALEV |
| Deputy Reinf. Concrete | 5/12/2023 | Approved | VASIL MIHALEV |
| Deputy Reinf. Concrete | 9/29/2023 | Partial Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 9/29/2023 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 9/29/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 10/3/2023 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 10/12/2023 | Conditional Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 10/13/2023 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/13/2023 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 10/18/2023 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 2/4/2025 | Approved | KENNETH NAGLE |
| Masonry Wall/Backfill | 2/4/2025 | Partial Approval | JOHNNY MIRANDA |
| Final | 4/24/2025 | Permit Finaled | JOHNNY MIRANDA |