11345 W VENTURA BLVD 91604

Certificate Information: 11345 W VENTURA BLVD 91604

Application / Permit
22020-20000-01203
Plan Check / Job No.
B22VN08212
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
PILE SUPPORED RETAINING WALLS FOR (N) PARKING LOT
Permit Issued
Issued on 9/9/2022
Issuing Office
Valley
Current Status
Permit Finaled on 5/29/2024

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 NILOOFAR MEHRAIN
Corrections Issued 6/7/2022 NILOOFAR MEHRAIN
Quality Review Completed 6/9/2022 STEVEN KIM
Building Plans Picked Up 6/13/2022 APPLICANT
Plan Check Approved 8/11/2022 NILOOFAR MEHRAIN
Issued 9/9/2022 APPLICANT
Permit Finaled 5/29/2024 JOHN KITCKO

Permit Application Clearance Information

Miscellaneous Cleared 6/23/2022 RYAN LY
Miscellaneous Cleared 6/23/2022 RYAN LY
Miscellaneous Cleared 6/23/2022 RYAN LY
Specific Plan Cleared 6/23/2022 RYAN LY
ZA Case Cleared 6/23/2022 RYAN LY
ZI Cleared 6/23/2022 RYAN LY
Excavation more than 5-ft deep Cleared 8/31/2022 CALOSHA APPROVED

Contact Information

Contractor Intertex Inc; Lic. No.: 482946-B 25134 RYE CANYON LOOP #300      VALENCIA, CA 91355
Engineer Hill,, Edward Foster; Lic. No.: GE2126 27865 AMBERWOOD LANE      VALENCIA, CA 91354
Engineer Mehta,, Manish Jitendra; Lic. No.: C54381 16600 SHERMAN WAY STE 180      VAN NUYS, CA 91406

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 11/17/2022 Approved JOHN KITCKO
Deputy Grading 11/18/2022 Approved JOHN KITCKO
Deputy Grading 11/21/2022 Conditional Approval DANNY RODRIGUEZ
Deputy Grading 11/22/2022 Approved JOHN KITCKO
Deputy Grading 11/23/2022 Approved JOHN KITCKO
Deputy Grading 11/28/2022 Conditional Approval JOHN KITCKO
Deputy Grading 12/1/2022 Approved JOHN KITCKO
Deputy Grading 12/2/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 12/2/2022 No Access for Inspection JOHN KITCKO
Deputy Grading 12/8/2022 Conditional Approval JEFFREY DURAN
Deputy Grading 12/9/2022 Conditional Approval BRUCE CAMPBELL
Deputy Grading 12/12/2022 Approved JOHN KITCKO
Deputy Grading 12/13/2022 Approved JOHN KITCKO
Deputy Grading 12/14/2022 Approved JOHN KITCKO
Deputy Grading 12/15/2022 Approved JOHN KITCKO
Deputy Grading 12/16/2022 Approved JOHN KITCKO
Deputy Grading 12/19/2022 Approved JOHN KITCKO
Deputy Grading 12/20/2022 Approved JOHN KITCKO
Deputy Grading 12/21/2022 Approved JOHN KITCKO
Deputy Grading 12/22/2022 Approved JOHN KITCKO
Piling/Pier/Caisson 12/22/2022 Partial Approval JOHN KITCKO
Deputy Grading 12/23/2022 Approved JOHN KITCKO
Deputy Reinf. Concrete 12/27/2022 Approved JOHN KITCKO
Deputy Grading 12/28/2022 Approved JOHN KITCKO
Deputy Grading 12/29/2022 Approved JOHN KITCKO
Deputy Grading 12/30/2022 Approved JOHN KITCKO
Deputy Other (see comments) 12/30/2022 Conditional Approval DEANDRE HOFFMAN
Excavation/Setback/Form/Re-Bar 1/27/2023 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 1/30/2023 No Access for Inspection ROBERT DAVIS
Piling/Pier/Caisson 1/30/2023 No Access for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 1/31/2023 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 2/14/2023 Corrections Issued JOHN KITCKO
Piling/Pier/Caisson 2/16/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 2/21/2023 Approved JOHN KITCKO
Piling/Pier/Caisson 2/22/2023 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 2/23/2023 Conditional Approval ROBERT DAVIS
Piling/Pier/Caisson 2/23/2023 Partial Approval ROBERT DAVIS
Deputy Grading 3/14/2023 Conditional Approval JOHN KITCKO
Deputy Shotcrete 4/7/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 4/7/2023 Not Ready for Inspection JOHN KITCKO
Reinforced Concrete Frame 4/7/2023 Not Ready for Inspection JOHN KITCKO
Deputy Shotcrete 4/11/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 4/11/2023 Corrections Issued JOHN KITCKO
Deputy Reinf. Concrete 4/12/2023 Conditional Approval JOHN KITCKO
Footing/Foundation/Slab 4/12/2023 Not Ready for Inspection JOHN KITCKO
Footing/Foundation/Slab 4/13/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 4/14/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 4/17/2023 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 4/19/2023 Partial Approval JOHN KITCKO
Deputy Grading 4/24/2023 Conditional Approval JOHN KITCKO
Deputy Grading 4/25/2023 Approved JOHN KITCKO
Deputy Grading 4/26/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 4/26/2023 Conditional Approval JOHN KITCKO
Deputy Grading 4/27/2023 Conditional Approval JOHN KITCKO
Deputy Grading 4/28/2023 Approved JOHN KITCKO
Deputy Shotcrete 5/3/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 5/9/2023 Conditional Approval JOHN KITCKO
Piling/Pier/Caisson 5/10/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/12/2023 Approved JOHN KITCKO
Deputy Grading 5/15/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 5/22/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 5/24/2023 Approved JOHN KITCKO
Footing/Foundation/Slab 5/24/2023 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 5/25/2023 Approved JOHN KITCKO
Piling/Pier/Caisson 5/30/2023 Partial Approval JOHN KITCKO
Piling/Pier/Caisson 5/31/2023 Partial Approval CAMERON CHABAN
Reinforced Concrete Frame 7/13/2023 Partial Approval JOHN KITCKO
Deputy Shotcrete 7/14/2023 Approved JOHN KITCKO
Deputy Shotcrete 7/20/2023 Conditional Approval JOHN KITCKO
Reinforced Masonry Frame 7/21/2023 Partial Approval JOHN KITCKO
Reinforced Concrete Frame 7/24/2023 Partial Inspection JOHN KITCKO
Deputy Drilled-In Anchors 8/9/2023 Approved JOHN KITCKO
Deputy Shotcrete 8/9/2023 Approved JOHN KITCKO
Grading Pre-Inspection 9/6/2023 Partial Inspection JOHN KITCKO
Deputy Drilled-In Anchors 10/25/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 10/25/2023 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 10/27/2023 Approved JOHN KITCKO
Deputy Reinf. Masonry 10/30/2023 Approved JOHN KITCKO
Deputy Reinf. Concrete 11/1/2023 Approved JOHN KITCKO
Deputy Drilled-In Anchors 11/29/2023 Approved JOHN KITCKO
Deputy Drilled-In Anchors 1/16/2024 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/19/2024 Approved JOHN KITCKO
Deputy Reinf. Masonry 1/25/2024 Approved JOHN KITCKO
Deputy Reinf. Concrete 3/11/2024 Conditional Approval JOHN KITCKO
Final 5/7/2024 Not Ready for Inspection JOHN KITCKO
Final 5/29/2024 Permit Finaled JOHN KITCKO