9262 W THRUSH WAY 90069
Certificate Information: 9262 W THRUSH WAY 90069
- Application / Permit
- 22020-20000-01111
- Plan Check / Job No.
- B22VN07616
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- TWO (N) 10FT HIGH MAX (1 AT 117.33LF & 1 AT 78.33LF) RETAINING WALLS ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Valley
- Current Status
- Issued on 4/14/2023
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 6/2/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 6/2/2022 | STEVEN KIM |
| Applicant returned to address corrections | 9/29/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 10/27/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 11/9/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/13/2022 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/19/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 12/20/2022 | NILOOFAR MEHRAIN |
| Issued | 4/14/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2022 | JEANIE LAM |
| Landscape for retaining wall | Cleared | 9/29/2022 | NATHAN ROMINE |
| Roof/Waste drainage to street | Cleared | 11/17/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 12/13/2022 | NILOOFAR MEHRAIN |
| Disturb/Remove Protected Trees | Cleared | 4/5/2023 | ADALBERTO VERA |
Contact Information
| Contractor | J M A General Contractor; Lic. No.: 893018-B | 5817 MCDONIE AVENUE WOODLAND HILLS, CA 91367 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 6/30/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Grading | 7/7/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 7/11/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/11/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Grading | 7/12/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/13/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 7/17/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 7/17/2023 | Approved | ALEXANDER HELFER |
| Deputy Reinf. Concrete | 7/21/2023 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/20/2023 | Conditional Approval | RAUL BARAJAS |