19233 W WELLS DR 91356

Certificate Information: 19233 W WELLS DR 91356

Application / Permit
22020-20000-00937
Plan Check / Job No.
B22VN04930
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
TWO (N) RETAINING WALLS (1 @ 2.5FT HIGH MAX (676LF) & 1 @ 4FT HIGH MAX (490LF) PER IB P/BC-2020-002)
Permit Issued
Issued on 8/22/2022
Issuing Office
Valley
Current Status
Permit Finaled on 8/11/2023

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 NILOOFAR MEHRAIN
Corrections Issued 4/25/2022 NILOOFAR MEHRAIN
Quality Review Completed 4/28/2022 STEVEN KIM
Building Plans Picked Up 4/29/2022 APPLICANT
Applicant returned to address corrections 8/9/2022 NILOOFAR MEHRAIN
Plan Check Approved 8/15/2022 NILOOFAR MEHRAIN
Issued 8/22/2022 APPLICANT
Permit Finaled 8/11/2023 VASIL MIHALEV

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/5/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/5/2022 DAGOVERTO GUERRERO
Miscellaneous Cleared 8/10/2022 DANIEL CORONADO
Grading Pre-Inspection Cleared 8/15/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHARLES POWELL, (818) 374-4355 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2022 Approved VASIL MIHALEV
Special/Order Compliance 9/16/2022 Partial Inspection VASIL MIHALEV
Special/Order Compliance 9/21/2022 Corrections Issued VASIL MIHALEV
Special/Order Compliance 10/4/2022 Not Ready for Inspection VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 10/12/2022 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 11/18/2022 Not Ready for Inspection TIMOTHY POWELL
Excavation/Setback/Form/Re-Bar 12/19/2022 Partial Approval ROBERT PINA
Footing/Foundation/Slab 12/20/2022 Partial Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 1/6/2023 Approved VASIL MIHALEV
Excavation/Setback/Form/Re-Bar 1/23/2023 Partial Inspection MICHAEL TEMPLE
Final 3/8/2023 Not Ready for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 5/25/2023 Partial Inspection MICHAEL TEMPLE
Final 5/25/2023 Not Ready for Inspection MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 6/13/2023 Partial Approval ROBERT PINA
Final 8/1/2023 Partial Inspection MICHAEL TEMPLE
Final 8/3/2023 Not Ready for Inspection VASIL MIHALEV
Special/Order Compliance 8/3/2023 Not Ready for Inspection MICHAEL TEMPLE