1930 N WHITLEY AVE 90068
Certificate Information: 1930 N WHITLEY AVE 90068
- Application / Permit
- 22020-20000-00847
- Plan Check / Job No.
- B22VN05675
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Retaining Wall
- Work Description
- TWO (N) 6FT & 10FT HIGH MAX RETAINING WALLS (63l,F ON PILES)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 10/10/2023
Permit Application Status History
| Submitted | 4/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/3/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/5/2022 | STEVEN KIM |
| Building Plans Picked Up | 5/6/2022 | APPLICANT |
| Applicant returned to address corrections | 8/30/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 9/27/2022 | NILOOFAR MEHRAIN |
| Issued | 9/27/2022 | APPLICANT |
| Permit Finaled | 10/5/2023 | GREGORY POMISH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/21/2022 | DANG NGUYEN |
| Landscape for retaining wall | Cleared | 8/2/2022 | DANG NGUYEN |
| Roof/Waste drainage to street | Cleared | 8/15/2022 | THAN WIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2022 | THAN WIN |
| Excavation more than 5-ft deep | Cleared | 9/27/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 9/27/2022 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/26/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Reinforced Concrete Frame | 1/26/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 1/31/2023 | Partial Approval | TIMOTHY POWELL |
| Deputy Reinf. Concrete | 2/3/2023 | Conditional Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/7/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/8/2023 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/22/2023 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/11/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/12/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 4/13/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 4/19/2023 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 5/1/2023 | Partial Inspection | TIMOTHY POWELL |
| Special/Order Compliance | 5/2/2023 | Corrections Issued | TIMOTHY POWELL |
| Final | 10/5/2023 | Permit Finaled | GREGORY POMISH |