10505 N GLENOAKS BLVD 91331

Certificate Information: 10505 N GLENOAKS BLVD 91331

Application / Permit
22020-20000-00725
Plan Check / Job No.
B22VN04935
Group
Building
Type
Nonbldg-New
Sub-Type
Commercial
Primary Use
(23) Retaining Wall
Work Description
TWO (N) 7.5FT HIGH (221LF) CMU RETAINING WALLS PER ENG'R DESIGN
Permit Issued
Issued on 4/6/2023
Issuing Office
Valley
Current Status
Issued on 4/6/2023

Permit Application Status History

Submitted 4/1/2022 APPLICANT
Assigned to Plan Check Engineer 4/28/2022 NILOOFAR MEHRAIN
Corrections Issued 5/24/2022 NILOOFAR MEHRAIN
Quality Review Completed 5/26/2022 STEVEN KIM
Building Plans Picked Up 5/27/2022 APPLICANT
Applicant returned to address corrections 3/23/2023 NILOOFAR MEHRAIN
Applicant returned to address corrections 3/24/2023 NILOOFAR MEHRAIN
Plan Check Approved 4/4/2023 NILOOFAR MEHRAIN
Issued 4/6/2023 APPLICANT

Permit Application Clearance Information

"T" removal Cleared 2/8/2023 NATHAN ROMINE
Miscellaneous Cleared 2/8/2023 NATHAN ROMINE
"Q" conditions Cleared 2/21/2023 NATHAN ROMINE
Landscape for retaining wall Cleared 2/21/2023 NATHAN ROMINE
Roof/Waste drainage to street Cleared 2/25/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/28/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Adamian,, Garen; Lic. No.: C74459 215 N KENWOOD ST #306      GLENDALE, CA 91206

Inspector Information

JOHN KITCKO, (818) 374-1109 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2024 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 2/15/2024 Partial Approval DANNY RODRIGUEZ
Piling/Pier/Caisson 2/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Piling/Pier/Caisson 2/26/2024 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 3/28/2024 Partial Inspection DANNY RODRIGUEZ
Pre-Inspection 3/28/2024 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 3/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/29/2024 Not Ready for Inspection DANNY RODRIGUEZ
Footing/Foundation/Slab 3/29/2024 Partial Approval DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Reinforced Masonry Frame 4/18/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 4/19/2024 Partial Approval DANNY RODRIGUEZ
Reinforced Masonry Frame 4/19/2024 Not Ready for Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/8/2024 Partial Approval DANNY RODRIGUEZ
Footing/Foundation/Slab 5/8/2024 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 5/16/2024 Not Ready for Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 6/3/2024 Partial Approval GREGORY POMISH
Masonry Wall/Backfill 6/10/2024 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 6/11/2024 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 10/4/2024 Not Ready for Inspection DANNY RODRIGUEZ
Final 6/12/2026 Partial Inspection JOHN KITCKO