564 E REDFIELD AVE 90042

Certificate Information: 564 E REDFIELD AVE 90042

Application / Permit
22020-10000-02640
Plan Check / Job No.
B21LA14822
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
NEW RETAINING WALL UP TO 5' HT. X 55' LONG
Permit Issued
Issued on 11/22/2022
Issuing Office
Metro
Current Status
Permit Finaled on 10/2/2025

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 SAM CHANG
Corrections Issued 9/23/2021 SAM CHANG
Quality Review Completed 9/27/2021 EUGENE BARBEAU
Building Plans Picked Up 10/1/2021 APPLICANT
Applicant returned to address corrections 10/19/2021 SAM CHANG
Applicant returned to address corrections 6/9/2022 SAM CHANG
Applicant returned to address corrections 10/6/2022 SAM CHANG
Applicant returned to address corrections 11/3/2022 SAM CHANG
Plan Check Approved 11/21/2022 SAM CHANG
Issued 11/22/2022 APPLICANT
Permit Finaled 10/2/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/3/2022 SAM CHANG

Contact Information

Contractor Owner-Builder       ,
Engineer Frolenko,, Gary; Lic. No.: C27863 23 HITCHCOCK WAY #104      SANTA BARBARA, CA 93105
Engineer Heathcote,, Fred Roy; Lic. No.: C48316 1884 EASTMAN AVE STE 105      VENTURA, CA 93003
Engineer Miller,, Karen Lynn; Lic. No.: GE2257 6634 VALJEAN AVENUE      VAN NUYS, CA 91406

Inspector Information

JONATHAN HOM, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT HUGHES, (213) 482-7452 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/29/2022 Corrections Issued ROBERT HUGHES
Masonry Wall/Backfill 1/20/2023 Partial Approval LANNY MERRICK
Excavation/Setback/Form/Re-Bar 1/26/2023 Partial Approval LANNY MERRICK
Final 2/10/2023 Not Ready for Inspection LANNY MERRICK
Masonry Wall/Backfill 5/12/2025 Not Ready for Inspection RAMAZANALI ALMASI
Final 8/14/2025 Not Ready for Inspection RAMAZANALI ALMASI
Final 10/2/2025 Permit Finaled RAMAZANALI ALMASI