6300 W FOREST LAWN DR 90068
Certificate Information: 6300 W FOREST LAWN DR 90068
- Application / Permit
- 22020-10000-02504
- Plan Check / Job No.
- B22LA20921
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) RETAINING WALLS, STAIRS, & WALKWAYS FOR "GARDENS OF HERITAGE 42-45"
- Permit Issued
- Issued on 7/20/2023
- Issuing Office
- Current Status
- Issued on 7/20/2023
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | LAMAR DAVIS |
| Corrections Issued | 10/25/2022 | LAMAR DAVIS |
| Quality Review Completed | 11/2/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/21/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 12/8/2022 | APPLICANT |
| Plan Check Approved | 7/19/2023 | MAHNAZ NOURHASHEMI |
| Issued | 7/20/2023 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| Miscellaneous | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| ZA Case | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| ZA Case | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| ZA Case | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| ZA Case | Cleared | 12/19/2022 | MARITZA PRZEKOP |
| DAS Clearance | Cleared | 4/21/2023 | EDDIE GARIN |
| Grading Pre-Inspection | Cleared | 5/12/2023 | LAMAR DAVIS |
| CPC | Cleared | 6/30/2023 | ERIN STRELICH |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/16/2024 | Approved | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 10/25/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 10/30/2024 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 11/8/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 11/21/2024 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 12/10/2024 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 12/16/2024 | Partial Approval | MARTIN TAVITIAN |
| Deputy Reinf. Concrete | 12/19/2024 | Conditional Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Partial Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 1/2/2025 | Partial Approval | LUIS CCAMACHO |
| Excavation/Setback/Form/Re-Bar | 1/10/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Partial Approval | TIMOTHY POWELL |
| Piling/Pier/Caisson | 6/12/2025 | Partial Inspection | TIMOTHY POWELL |
| Piling/Pier/Caisson | 6/13/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/16/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 7/2/2025 | Partial Approval | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 7/16/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 7/18/2025 | Partial Approval | DAVID BURKHEAD |
| Deputy Reinf. Concrete | 10/1/2025 | Conditional Approval | CHRISTOPHER BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Partial Approval | CHRISTOPHER BLACKWOOD |
| Final | 5/26/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |