1923 W BAXTER ST 90039
Certificate Information: 1923 W BAXTER ST 90039
- Application / Permit
- 22020-10000-02410
- Plan Check / Job No.
- B22LA20034
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- eplan Design of new retaining wall (43ft), due to defective existing retaining wall at west property line.
- Permit Issued
- Issued on 6/22/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/8/2024
Permit Application Status History
| Submitted | 10/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 11/7/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 11/14/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/17/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 5/11/2023 | MARCELA FRANQUEZ |
| Issued | 6/22/2023 | APPLICANT |
| Permit Finaled | 11/7/2024 | COREY HUPP |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/17/2023 | MARCELA FRANQUEZ |
| Hold | Cleared | 10/16/2023 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
| Geologist | Rahimikian,, Pedram; Lic. No.: EG2683 | 21414 ARCOS DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 6/11/2024 | Corrections Issued | COREY HUPP |
| Reinforced Concrete Frame | 6/20/2024 | Approved | EMIL OPFFER |
| Special/Order Compliance | 6/26/2024 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Approved | COREY HUPP |
| Footing/Foundation/Slab | 9/17/2024 | Approved | COREY HUPP |
| Grading Pre-Inspection | 9/23/2024 | Approved | EMIL OPFFER |
| Masonry Wall/Backfill | 9/26/2024 | Approved | COREY HUPP |
| Final | 11/7/2024 | Permit Finaled | COREY HUPP |