3020 W WILSHIRE BLVD 90010

Certificate Information: 3020 W WILSHIRE BLVD 90010

Application / Permit
22020-10000-02233
Plan Check / Job No.
B22LA18779
Group
Building
Type
Nonbldg-New
Sub-Type
Apartment
Primary Use
(23) Shoring (Temporary)
Work Description
EPLAN SHORING for NEW 8-STORY 262 UNITS MIXED USE BUILDING TO INCLUDE 6 LEVELS OF TYPE IIIA APARTMENT OVER 2-STORY TYPE IA PARKING/RETAIL OVER 1 LEVEL SUBTERRANEAN PARKING TO INCLUDE RACKER AND TIEBACKS
Permit Issued
Issued on 8/31/2023
Issuing Office
Metro
Current Status
Permit Finaled on 6/30/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/29/2022 APPLICANT
Assigned to Plan Check Engineer 10/13/2022 QUAN NGHIEM
Corrections Issued 10/27/2022 QUAN NGHIEM
Quality Review Completed 11/3/2022 CHAD DOI
Plan Check Approved 5/4/2023 QUAN NGHIEM
Issued 8/31/2023 APPLICANT
Permit Finaled 6/29/2026 JOEY BUCHANAN

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 4/11/2023 KHOUNG LE
Metro Rail approval Cleared 8/3/2023 SHINE LING

Contact Information

Contractor Owner-Builder       ,
Engineer Cefali,, David Allen; Lic. No.: NA3658       ,
Engineer Cefali,, David Allen; Lic. No.: S3658 4344 LAUREL CANYON BLVD_STE 3      STUDIO CITY, CA 91604

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 4/24/2024 Partial Approval LUIS CCAMACHO
Deputy Steel/Welding 4/24/2024 Partial Approval LUIS CCAMACHO
Piling/Pier/Caisson 4/24/2024 Partial Approval LUIS CCAMACHO
Deputy Grading 5/1/2024 Conditional Approval NICK DANERI
Piling/Pier/Caisson 5/1/2024 Partial Approval NICK DANERI
Piling/Pier/Caisson 5/8/2024 Partial Inspection RAMAZANALI ALMASI
Piling/Pier/Caisson 5/15/2024 Partial Inspection JACOB MYERS
Deputy Reinf. Concrete 5/22/2024 Conditional Approval NICK DANERI
Piling/Pier/Caisson 5/22/2024 Partial Inspection NICK DANERI
Deputy Grading 5/29/2024 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/29/2024 Conditional Approval NICK DANERI
Piling/Pier/Caisson 5/29/2024 Partial Approval NICK DANERI
Piling/Pier/Caisson 6/4/2024 Partial Approval NICK DANERI
Deputy Grading 6/5/2024 Conditional Approval NICK DANERI
Piling/Pier/Caisson 6/11/2024 Partial Inspection NICK DANERI
Final 6/29/2026 Permit Finaled JOEY BUCHANAN