3388 S MANNING CT 90064

Certificate Information: 3388 S MANNING CT 90064

Application / Permit
22020-10000-02185
Plan Check / Job No.
B22LA18287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD COVERED PATIO TO THE REAR OF THE EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/26/2023
Issuing Office
Current Status
CofO Issued on 10/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 GEORGE ALVAREZ
Corrections Issued 9/18/2022 GEORGE ALVAREZ
Applicant returned to address corrections 9/29/2022 SHANGQIN XIE
Applicant returned to address corrections 1/5/2023 SHANGQIN XIE
Plan Check Approved 1/16/2023 JOSEPH RAFOLS
Issued 1/26/2023 APPLICANT
CofO in Progress 10/13/2023 CLAYTON GRAHAM
Permit Finaled 10/25/2023 DANIEL ORRANTE
CofO Issued 10/25/2023 DANIEL ORRANTE
Permit Finaled 10/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 10/3/2022 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 10/7/2022 DINAH GARIN
Grading Pre-Inspection Cleared 10/11/2022 KIRK LINKLATER
Specific Plan Cleared 10/12/2022 ROBERT SANCHEZ
Low Impact Development Cleared 12/29/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 1/4/2023 JENSON LEE

Contact Information

Architect Lopez,, Craig Joseph; Lic. No.: C14263 1836 CALLE ALBERCA      CAMARILLO, CA 93010
Contractor Mateo Construction Inc; Lic. No.: 1066115-B       ,

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/15/2023 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 3/3/2023 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 3/3/2023 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 4/19/2023 Corrections Issued CLAYTON GRAHAM
Green Building Rough 4/19/2023 Not Ready for Inspection CLAYTON GRAHAM
MERV13>=Rough 4/19/2023 Not Ready for Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 6/1/2023 Corrections Issued CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 6/1/2023 Approved CLAYTON GRAHAM
BUILDING-Rough-Frame 6/30/2023 Approved CLAYTON GRAHAM
Green Building Rough 6/30/2023 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 6/30/2023 Partial Approval CLAYTON GRAHAM
SGSOV-Seismic Gas S/O Valve 8/1/2023 SGSOV Not Ready CLAYTON GRAHAM
Final 8/28/2023 Corrections Issued DAVID FEILER
Green Building Final 8/28/2023 Not Ready for Inspection DAVID FEILER
MERV13>=Final 8/28/2023 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved DAVID FEILER
Smoke Detectors 8/28/2023 Approved DAVID FEILER
Final 10/13/2023 OK to Issue CofO CLAYTON GRAHAM
Green Building Final 10/13/2023 Approved CLAYTON GRAHAM