3689 W SHANNON ROAD 90027

Certificate Information: 3689 W SHANNON ROAD 90027

Application / Permit
22020-10000-02072
Plan Check / Job No.
B22LA17467
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
DISTRESSED RETAINING WALL BYPASS & REPLACEMENT. INTEGRATED STRUCUTRAL DECK 1 of 2
Permit Issued
Issued on 1/5/2023
Issuing Office
Current Status
Permit Finaled on 10/27/2023

Permit Application Status History

Submitted 8/31/2022 APPLICANT
Assigned to Plan Check Engineer 9/1/2022 CARLOS MONTES
Corrections Issued 9/6/2022 CARLOS MONTES
Quality Review Completed 9/15/2022 KEN GILL
Building Plans Picked Up 9/16/2022 APPLICANT
Applicant returned to address corrections 11/14/2022 CARLOS MONTES
Plan Check Approved 12/22/2022 CARLOS MONTES
Issued 1/5/2023 APPLICANT
Permit Finaled 10/26/2023 JOSEPH MCGARRY

Permit Application Clearance Information

Landscape for retaining wall Cleared 11/8/2022 DANIEL CORONADO
Excavation more than 5-ft deep Cleared 12/22/2022 CALOSHA APPROVED
Grading Pre-Inspection Cleared 12/22/2022 CARLOS MONTES

Contact Information

Contractor Alpha Structural Inc; Lic. No.: 663409-B 8334 FOOTHILL BLVD      SUNLAND, CA 91040
Engineer Su,, Yu-Ting; Lic. No.: C76714 28 SAGE      LAKE FOREST, CA 92630
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 3/28/2023 No Access for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 3/29/2023 Partial Approval JOSEPH MCGARRY
Piling/Pier/Caisson 3/29/2023 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/5/2023 Not Ready for Inspection JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/11/2023 Partial Approval JOSEPH MCGARRY
Piling/Pier/Caisson 4/11/2023 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 4/12/2023 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 4/12/2023 Partial Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/17/2023 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 4/18/2023 Partial Approval JOSEPH MCGARRY
Deputy Shotcrete 4/24/2023 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 5/15/2023 Approved JOSEPH MCGARRY
Wood Frame 5/15/2023 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 5/18/2023 Conditional Approval SCOTT FINNILA
Final 10/26/2023 Permit Finaled JOSEPH MCGARRY