2500 N ASTRAL DR 90046
Certificate Information: 2500 N ASTRAL DR 90046
- Application / Permit
- 22020-10000-01863
- Plan Check / Job No.
- B22LA15738
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- *EPLAN* NEW RETAINING WALL (MAX 12' HIGH, 102 LINEAR FEET)WITH DECK
- Permit Issued
- Issued on 1/22/2025
- Issuing Office
- Current Status
- Issued on 1/22/2025
Permit Application Status History
| Submitted | 8/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2022 | SELLA BENYAMIN |
| Corrections Issued | 9/8/2022 | SELLA BENYAMIN |
| Quality Review Completed | 9/21/2022 | STEVEN KIM |
| Quality Review Completed | 9/21/2022 | STEVEN KIM |
| Applicant returned to address corrections | 6/28/2024 | SELLA BENYAMIN |
| Plan Check Approved | 1/2/2025 | SELLA BENYAMIN |
| No Progress | 1/15/2025 | SELLA BENYAMIN |
| Plan Check Approved | 1/15/2025 | SELLA BENYAMIN |
| Issued | 1/22/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/17/2024 | JUDE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 8/1/2024 | AMBER CAMPBELL |
Contact Information
| Contractor | Construction Unlimited Builders Inc; Lic. No.: 1028070-B | , |
| Engineer | Liu,, Haiyan Harry; Lic. No.: NA81463 | , |
| Engineer | Riley,, Gregory Leo; Lic. No.: C56052 | POSTAL BOX 1622 TEHACHAPI, CA 93581 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/28/2025 | Approved | PTOLEMY HILL |
| Deputy Reinf. Concrete | 5/7/2025 | Approved | JOEL ORDAZ |
| Excavation/Setback/Form/Re-Bar | 6/20/2025 | Approved | JONATHAN FRANCHINI |
| Deputy Reinf. Concrete | 6/26/2025 | Approved | JOEL ORDAZ |
| Piling/Pier/Caisson | 8/6/2025 | Approved | PTOLEMY HILL |
| Deputy Reinf. Concrete | 8/12/2025 | Approved | JOEL ORDAZ |
| Footing/Foundation/Slab | 10/15/2025 | Approved | JOEL ORDAZ |
| Footing/Foundation/Slab | 10/28/2025 | Approved | JOEL ORDAZ |
| Deputy Reinf. Concrete | 10/29/2025 | Approved | JOEL ORDAZ |