4611 S CRENSHAW BLVD 90043
Certificate Information: 4611 S CRENSHAW BLVD 90043
- Application / Permit
- 22020-10000-01860
- Plan Check / Job No.
- B22LA15726
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Shoring (Temporary)
- Work Description
- Early Start Permit for Shoring for new building under BP# 21010 - 10000 - 04874
- Permit Issued
- Issued on 2/28/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/15/2025
- Certificate of Occupancy
- TCO Issued More Information
Permit Application Status History
| Submitted | 8/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2022 | HERNAN ARREOLA |
| Corrections Issued | 9/5/2022 | HERNAN ARREOLA |
| Quality Review Completed | 9/7/2022 | GARO TELMI |
| Applicant returned to address corrections | 10/20/2022 | HERNAN ARREOLA |
| Plan Check Approved | 12/28/2022 | HERNAN ARREOLA |
| Issued | 2/28/2023 | APPLICANT |
| Permit Finaled | 4/15/2025 | JAMES POWERS |
Permit Application Clearance Information
| Bicycle Parking | Cleared | 9/12/2022 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2022 | CHRISTOPHER ROCHA |
| Miscellaneous | Cleared | 9/13/2022 | CINDY QI |
| CPC | Cleared | 9/19/2022 | KENTON TRINH |
| Frnt yard landscape/Water mgmt | Cleared | 9/19/2022 | KENTON TRINH |
| Excavation more than 5-ft deep | Cleared | 10/6/2022 | CALOSHA APPROVED |
| "D" conditions | Cleared | 12/8/2022 | DANIEL CORONADO |
| Site Plan review | Cleared | 12/8/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 12/9/2022 | DANIEL CORONADO |
| ZA Case | Cleared | 12/9/2022 | DANIEL CORONADO |
| Redevelopment Project Area | Cleared | 12/13/2022 | GRACIELA ACOSTA |
| Density Bonus 12.22.A.31 | Cleared | 12/15/2022 | DORIS KWOK |
| Work Adjacent to Public Way | Cleared | 12/23/2022 | KHOUNG LE |
Contact Information
| Architect | Watts,, Jonathan Venning; Lic. No.: NA21311 | , |
| Contractor | Suffolk Construction Company Inc; Lic. No.: 751099-B | , |
| Contractor | Suffolk-Roel; Lic. No.: 751099-B | , |
| Engineer | Salter,, David R; Lic. No.: C69911 | 3445 CEDAR ST SANTA YNEZ, CA 93460 |
| Engineer | Tang,, Stanley Siu Kei; Lic. No.: C56178 | 1105 N AVON STREET BURBANK, CA 91505 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 5/18/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Steel/Welding | 5/18/2023 | Approved | ALAN MORELOS |
| Pre-Inspection | 5/18/2023 | Approved | ALAN MORELOS |
| Deputy Steel/Welding | 5/19/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 5/31/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/1/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/2/2023 | Conditional Approval | JULIAN CAPUCETTI |
| Piling/Pier/Caisson | 6/2/2023 | Partial Inspection | JULIAN CAPUCETTI |
| Deputy Grading | 6/5/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/9/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Piling/Pier/Caisson | 7/6/2023 | Approved | JULIAN CAPUCETTI |
| Deputy Shotcrete | 8/2/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Grading | 1/2/2024 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 1/3/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2024 | Partial Approval | JAMES POWERS |