506-510 N SYCAMORE AVE 90036
Certificate Information: 506-510 N SYCAMORE AVE 90036
- Application / Permit
- 22020-10000-01733
- Plan Check / Job No.
- B22LA14703
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Retaining Wall
- Work Description
- (N) 6' CMU/RETAINING WALL PERMIT FOR THE 5-UNIT SMALL LOT SUBDIVISION PROJECT PER VTT-82842-SL
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 6/3/2026
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | SERGIO GUTIERREZ |
| Corrections Issued | 8/2/2022 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/5/2022 | KEN GILL |
| Building Plans Picked Up | 8/15/2022 | APPLICANT |
| Applicant returned to address corrections | 12/16/2022 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 5/31/2023 | SERGIO GUTIERREZ |
| Plan Check Approved | 8/11/2023 | SERGIO GUTIERREZ |
| Issued | 9/8/2023 | APPLICANT |
| Permit Finaled | 6/2/2026 | AL GAMBLE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/11/2023 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 5/11/2023 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 5/11/2023 | SPENCER WEJROWSKI |
| Stormwater Pollution Mitigatn | Cleared | 5/15/2023 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Contractor | Sunny Construction & Development Corporation; Lic. No.: 737977-B | 711 S FIRST AVE ARCADIA, CA 91006 |
| Engineer | Jones,, Ryan Keith; Lic. No.: GE2852 | 1253 W MASLINE ST COVINA, CA 91722 |
| Engineer | Jong,, Hank Hsing-Lian; Lic. No.: C45846 | 11819 GOLDRING ROAD UNIT A ARCADIA, CA 91006 |
Inspector Information
| AL GAMBLE, (213) 482-0403 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/6/2023 | Corrections Issued | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Corrections Issued | JONATHAN HOM |
| Masonry Wall/Backfill | 12/7/2023 | Partial Approval | JONATHAN HOM |
| Footing/Foundation/Slab | 12/11/2023 | Approved | ALEXANDER HELFER |
| Reinforced Masonry Frame | 12/11/2023 | Approved | ALEXANDER HELFER |
| Deputy Grading | 12/14/2023 | Approved | JONATHAN HOM |
| Deputy Reinf. Concrete | 12/15/2023 | Approved | JONATHAN HOM |
| Footing/Foundation/Slab | 12/15/2023 | Partial Approval | JONATHAN HOM |
| Masonry Wall/Backfill | 12/28/2023 | Approved | ALEXANDER HELFER |
| Reinforced Masonry Frame | 1/3/2024 | Partial Approval | RUSSELL BONVOULOIR |
| Footing/Foundation/Slab | 1/11/2024 | Partial Approval | JONATHAN HOM |
| Reinforced Masonry Frame | 1/16/2024 | Approved | ALEXANDER HELFER |
| Footing/Foundation/Slab | 1/18/2024 | Partial Approval | ROBERT PINA |
| Masonry Wall/Backfill | 1/18/2024 | Partial Approval | ROBERT PINA |
| Footing/Foundation/Slab | 1/19/2024 | Partial Approval | ROBERT PINA |
| Deputy Reinf. Concrete | 1/22/2024 | Approved | JONATHAN HOM |
| Reinforced Masonry Frame | 1/26/2024 | Approved | ALEXANDER HELFER |
| Reinforced Masonry Frame | 1/29/2024 | Partial Inspection | JONATHAN HOM |
| Reinforced Masonry Frame | 1/30/2024 | Partial Approval | JONATHAN HOM |
| Reinforced Masonry Frame | 2/12/2024 | Partial Approval | JONATHAN HOM |
| Reinforced Masonry Frame | 2/16/2024 | Partial Approval | JONATHAN HOM |
| Deputy Drilled-In Anchors | 6/26/2024 | Approved | JONATHAN HOM |
| Final | 5/18/2026 | Not Ready for Inspection | AL GAMBLE |
| Final | 6/2/2026 | Permit Finaled | AL GAMBLE |