821 N GLENMERE WAY 90049

Certificate Information: 821 N GLENMERE WAY 90049

Application / Permit
22020-10000-01659
Plan Check / Job No.
B22LA10553
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Retaining Wall
Work Description
EPLAN 2 NEW RETAINING WALLS FOR NEW SFD (SEE PLOT PLAN FOR LOCATION)
Permit Issued
Issued on 6/5/2025
Issuing Office
Current Status
Issued on 6/5/2025

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 MARCELA FRANQUEZ
Corrections Issued 7/19/2022 MONICA RAMIREZ
Quality Review Completed 7/20/2022 RODOLFO ARIAS
Plan Check Approved 3/28/2025 MARCELA FRANQUEZ
Issued 6/5/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/5/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 8/16/2022 ANTHONY MAINEZ
Watercourse Cleared 8/18/2022 ANTHONY MAINEZ
Miscellaneous Cleared 9/14/2022 SAUL GARCIA
Landscape for retaining wall Cleared 12/11/2024 MATHEW QUAN

Contact Information

Contractor Hershel Construction Inc; Lic. No.: 780613-B       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Mahmoudkhani,, Behnam; Lic. No.: C88488 1718 W PARKSIDE AVE      BURBANK, CA 91506
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

GERMAN RODRIGUEZ MENDOZA, (310) 914-3932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 6/11/2025 Corrections Issued MATTHEW JENKINS
Piling/Pier/Caisson 6/24/2025 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 7/1/2025 Corrections Issued JOHNNY MIRANDA
Piling/Pier/Caisson 7/2/2025 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 7/8/2025 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 7/15/2025 Corrections Issued JOHNNY MIRANDA
Piling/Pier/Caisson 7/24/2025 Not Ready for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 8/4/2025 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 8/11/2025 Partial Approval JOHNNY MIRANDA
Piling/Pier/Caisson 8/18/2025 Partial Inspection MATTHEW JENKINS
Footing/Foundation/Slab 10/10/2025 Not Ready for Inspection JOHNNY MIRANDA